IT project management

IT project management — the practice of steering a project from idea to acceptance, on time and on budget. In this reference: the technical specification, Scrum and Kanban, roles, risks, contracts, metrics.

checked 7 Nov · next check 14 Nov · 82 min read

Sections
14
Reading
82 min
Languages
RU · UZ · EN
Written from
scrumguides.org/scrum-guide.html

Check status of the reference

Verified 7 Nov · next check 14 Nov

The sections were compared with the release notes, the check found nothing, and all source links respond.

  1. Verified
  2. Scheduled check

What IT project management is and how it works

A project is temporary work for a unique result: implementing a CRM, moving to the cloud, delivering a release. Project management is the application of knowledge, skills, tools and techniques to project activities to meet the project’s requirements (the definition of PMI, the Project Management Institute).

A project differs from operational work in its uniqueness. Operational work is processes that run continuously: user support, backups, updates. A project ends when the result has been achieved. ISO 21500:2021 defines the concepts of project, programme and portfolio: a programme is several related projects managed together for a common benefit; a portfolio is all the projects and programmes of an organisation, selected to serve its goals.

AspectProjectOperational work
Durationhas a start and an end: implementing a CRM in 6 monthscontinuous: daily support of the same CRM
Resultunique: no such CRM existed beforerepetitive: the same tickets and reports
Teamassembled for the project and disbandedpermanent roles with no end date
How success is measureddelivered on time, on budget and within the specified scopestability: availability and response time

A project has four interdependent constraints: scope, schedule, cost and quality. Moving one without the others never works. If the customer asks to shorten a CRM implementation from 6 to 4 months, you have to cut the scope — defer some of the features — or add people and money. Quality is never the buffer: less testing means not savings but defects that users will find.

A project and a product are different things with different ends. A project ends with acceptance of the result; after that the product lives in operation for years, until decommissioning. Project success is measured by delivery on time and on budget, product success by the value for users.

Several roles are responsible for the result; each one is covered in detail in the section “Roles and responsibility”:

  • sponsor (customer) — owns the money and the goals; accepts the result;
  • project manager — plans, coordinates and reports; is responsible for the schedule, the budget and the scope;
  • Product Owner — decides what the team does and in what order;
  • team — the specialists who do the work;
  • stakeholders — everyone the result affects: users, contractors, the operations team.

The life cycle from idea to operation

Projects share the same phases and differ in how deeply each one is worked through; the kinds of life cycle models are covered in detail in the section “Life cycle models”. GOST R 59793-2021 describes the same stages in different words: requirements definition, concept development, technical specification, preliminary design, detailed design, working documentation, commissioning and maintenance. ISO/IEC/IEEE 12207 covers the full software life cycle, including operation and decommissioning.

  1. Business case — why the project exists: the business goal, the expected benefit, a preliminary estimate.
  2. Initiation — a project manager is appointed, the charter and the technical specification are approved; the project receives money and authority.
  3. Planning — scope, schedule, budget, risks and the communication plan.
  4. Execution and control — the team does the work; the manager keeps track of the schedule, the budget and changes.
  5. Acceptance and handover — the customer checks the result against the acceptance criteria and accepts it.
  6. Operation — the product runs outside the project: maintenance, further development, decommissioning.
The stages of GOST R 59793-2021 cover the same path: from requirements definition to commissioning and maintenance.

The project ends at acceptance — after that the result lives a life of its own. Decisions about the product, operation and technical debt continue to be made without the project team. So it pays to decide at the planning stage who will maintain the system after handover.

How it differs from related disciplines

DisciplineWhat is at the centreWho is responsibleWhen it ends
Project managementa unique result within a given scope, schedule and budgetproject managerwith acceptance of the result
Product managementthe value of the product: user needs and developmentproduct managerwith the product’s decommissioning
IT service management (ITSM)stable services: incidents, requests, changesthe operations teamit never ends while the service lives
Programme managementrelated projects with a common resultprogramme managerwhen the programme goals are achieved

The boundary is simple: project management ends with acceptance, while the product, the service and the programme live longer — they have different roles and different criteria of success.

What you need to know in advance

No prior knowledge is required: the section starts from zero. Related references will come in handy once you reach practice: how the quality of the result is checked — “Test design”; how a system is described — “Software architecture”; how built code reaches operation — “CI/CD”.

Section sources

the section is written from these pages

Project start checklist

A start checklist for an IT project: 25 checks a team’s work begins with. Go through it before work starts, when the project manager changes and before a contract is signed. A skipped item usually surfaces at the end as a dispute over scope, deadlines or money.

Each item is a testable statement in the imperative; the conditions that apply and the definitions are in the working sections of the reference, which the “see the section” notes point to. The items follow the order in which a project is usually started: first the goal and the scope, then people, plan, contract, process and risks.

Goal and rationale

  • Write the project goal as one sentence with a measurable result and a deadline — phrased so that you can tell from it whether the project succeeded or not.
  • Approve the business case and name the sponsor — the person who decides on the money and accepts the result — see the section “Project economics”.
  • Write down the project’s stop condition — the stop criterion: at what result or deadline the work is stopped, so that the project is not dragged on for the sake of what has already been invested — see the section “Project economics”.

Scope and requirements

  • Agree on the technical specification or an ordered backlog — the single source of the team’s work; the list of specification sections is given in GOST 34.602-2020, see the section “Requirements and specifications”.
  • Write down what is outside the scope: a list of exclusions settles disputes about “small tweaks” in the middle of a project.
  • For each requirement, give an acceptance criterion — a testable condition the customer will accept the result against.
  • Write down the non-functional requirements with numbers: response time, number of users, availability — see the section “Requirements and specifications”.

People and decisions

  • Appoint one owner of product decisions — not a committee: the “customer is right, contractor is right” dispute must end with a name.
  • Build a RACI matrix for the key decisions — exactly one “A” in a row; for the role breakdown, see the section “Roles and responsibilities”.
  • Put the stakeholders in a register with their interests and how to reach them.
  • Agree on the channels: where a task lives, where discussion happens, what counts as a decision and where the history is kept.

Plan and budget

  • Build a WBS (work breakdown structure) down to work packages you can manage and estimate — see the section “Estimation and planning”.
  • Give estimates as a range, not an exact date, and write down what went into the calculation.
  • Budget the reserve for known risks as a separate budget line, not as a percentage “on top”.
  • Publish a roadmap with milestones and the criteria by which they are judged.

Contract and acceptance

  • Choose the contract type — Fixed Price or T&M — by how stable the scope is; for how the risks are shared, see the section “Procurement and contracts”.
  • Describe the acceptance procedure: who accepts, against which criteria and how many days are allowed for fixing the issues raised.
  • Sign an NDA (non-disclosure agreement) before internal data is handed to the contractor.
  • Agree on an SLA (service level agreement) for support after launch, while the terms can still be discussed — see the section “Procurement and contracts”.

Process

  • Fix the sprint length — no more than a month — and the Definition of Done: a formal description of a complete increment, the same for the whole team.
  • Set up a task tracker and a wiki for architecture decision records (ADRs).
  • Set the day and the format of the status report: what to report, to whom and against which metrics.

Risks and changes

  • Start a risk register with the probability, impact and owner of every risk — see the section “Risks and changes”.
  • Describe the change request procedure: the form, the assessment of consequences and who approves it.
  • Find the tasks only one person knows (the bus factor) and assign a second person to each.

Section sources

the section is written from these pages

Life cycle models

A life cycle model is the order of the project stages and the feedback loops between them: what goes in sequence, what repeats and when the customer sees the result. ISO/IEC/IEEE 12207 describes life cycle processes but does not require any specific model — the project chooses it.

The standard states this explicitly: processes are applied concurrently, iteratively and recursively — to the system as a whole and incrementally to its elements — and it does not prescribe a specific model, method or way of choosing a model for an organisation or a project. The current second edition, ISO/IEC/IEEE 12207:2026 (April 2026), replaced the 2017 edition. The choice between waterfall, iterative and hybrid development is made by the project manager together with the customer. The contract, the plan and the set of documents depend on this choice.

The waterfall model

The waterfall model: the stages run in sequence — requirements, design, code, testing, delivery — and the next one starts after the previous one is complete. The customer sees the result once, at the end. The model is appropriate when requirements are stable, a mistake is expensive and the regulator requires a complete set of documents before development: a system for a bank, medical software, a state defence order.

The model is attributed to Winston Royce. In his 1970 paper he drew a sequential scheme “requirements → design → coding → testing → operation” — and called it risky. Testing at the end of the cycle shows, for the first time, real response time, memory usage and I/O rather than calculated estimates. If the results do not fit within the constraints, a redesign follows, with schedule and cost overruns of up to 100%. The word “waterfall” does not appear in the paper.

Instead of pure waterfall Royce proposed five steps. First, a preliminary program design before analysis; then a complete set of documentation; then doing it twice: a pilot version checks the concept before the main development; then test planning and control; and customer involvement at points after the requirements definition. The modern “waterfall” is a simplification of this scheme without the feedback loops.

Iterative and incremental development

Iterative development repeats the cycle “design → build → show” several times; incremental development delivers the result in growing parts, each of which has users. Feedback after each iteration reduces the price of a requirements error: it is found after two weeks rather than at acceptance six months later.

Example: a CRM implementation. The first iteration is the customer card and search; the second is deals and the pipeline; the third is reports and import from the legacy system. After each iteration the sales department works with the system and refines the requirements for the next one.

Agile approaches

Agile development (AgileAgileAn approach to software development in which teams work in short cycles, release working software frequently and adapt to changing requirements.Read more: Agile) is a family of approaches that grew out of iterative development. The Agile Manifesto of 2001 distinguishes four values:

We value moreOver
individuals and interactionsprocesses and tools
working softwarecomprehensive documentation
customer collaborationcontract negotiation
responding to changefollowing a plan

The values do not forbid plans and documents: they say what to spend time on first when resources are limited. Scrum and Kanban are two specific frameworks built on these values: how sprints, events and artifacts work — in the section “Scrum and Kanban”.

Hybrid approaches

PMI distinguishes three approaches. Predictive: the requirements are known and stable at the start, the plan is detailed, and the phases follow one another. Adaptive: the requirements change and are refined along the way. Hybrid combines the two. It is appropriate when part of the project is stable and is documented, while another part changes quickly.

Example: an integration with a bank. Message exchange and testing proceed according to the technical specification and GOST — the predictive part. The personal account interface and the calculation formulas are reworked in sprints according to user feedback — the adaptive part.

The software life cycle and system development stages

The software development life cycle (SDLCSDLCsoftware development life cycleThe set of stages software goes through: from the idea and the requirements to maintenance and retirement.Read more: SDLC) is part of the life cycle of the whole system: hardware, staff and procedures each have their own cycles, and all of them converge at commissioning. The stages of automated system development are set by GOST R 59793-2021: requirements definition, concept development, technical specification, preliminary design, technical design, working documentation, commissioning, maintenance. Older documents mention GOST 34.601-90 — the former standard of stages.

The same requirements error costs more in waterfall: by the time it is found, the whole project is ready.

How to choose a model

The model is chosen before the contract and the plan: it determines what to fix in the contract, which documents to agree on before development and when the customer will see the result. The decision is based on five conditions:

ConditionWaterfallIterative or agileHybrid
Requirementsstable and knownrefined along the waya stable core, a changing interface
Access to the customerat the start and at acceptanceafter each iterationrare on the stable part, frequent on the flow
Contractfixed scope, schedule and priceteam and time, scope is refinedfixed scope + repeat purchases
Regulatorrequires the full set before developmentallows staged deliveriesdocuments for the core, releases for the flow
Cost of a late changehigh: a project redesignlow: fixes in the next iterationdepends on the part of the project

If the conditions contradict one another, the hybrid wins: the core with contractual liability — by waterfall, the fast-changing parts — in iterations. How “Agile without rules” looks in practice and how it ends — in the section “Common mistakes”.

More on this

The project stages from idea to acceptance are covered in the section “What IT project management is and how it works”. The technical specification and requirements — in the section “Requirements and specifications”, Scrum sprints and events — in the section “Scrum and Kanban”. Life cycle standards and their status — in the section “Standards and bodies of knowledge”.

Section sources

the section is written from these pages

Requirements and the technical specification

A requirement is a verifiable statement of what the system must do or what it must be. ISO/IEC/IEEE 29148:2018 defines three levels: business requirements, stakeholder requirements and system requirements; they are written down in a BRD, in user stories and in an SRS or, in government projects, in a GOST 34.602-2020 technical specification.

A system requirement is derived from a user one, and that in turn from a business requirement; only the lowest level can be checked for feasibility.

The documents on the right show where each level lives.
LevelWho states itDocumentExample
business requirementcustomer, sponsor, product managerBRD“cut request processing from 3 days to 1”
user requirementoperator, client, analystStRS or a user story“the operator sees the client’s enquiry history”
system requirementanalyst together with the teamSRS“finding a client by phone number — no longer than 2 s”

Documents: BRD, SRS, PRD

DocumentWhoseWhen it is writtenWhat is inside
BRD — business requirementscustomer and sponsorbefore the solution is chosengoals and boundaries, business requirements, success criteria
SRS — software requirementsanalyst with the teamafter the BRD, before and during developmentfunctional requirements and NFRs, interfaces, constraints
PRD — product requirementsproduct managerin product companies, iterativelyuser problems, scenarios, release requirements

The SRS is an information element of 29148: the standard prescribes its sections and quality rules. The PRD has no standard — it is a practice of product teams; it often replaces the BRD and SRS with a single living document.

A GOST 34.602-2020 technical specification

In government and corporate projects requirements are drawn up as a technical specification for an automated system. The structure and content of the tech spec are set by GOST 34.602-2020 — in force since 1 January 2022 instead of GOST 34.602-89; changes to the tech spec are made by a supplement agreed in the same way as the tech spec itself. The mandatory sections:

Tech spec sectionWhat is in it
1. General informationsystem name, customer and contractor, plan and deadlines
2. Purpose and objectiveswhat we automate and for the sake of which indicators
3. Characteristics of the automation objectswhich processes and data the system touches
4. Requirements for the automated systemfunctions, reliability, security, ergonomics — the core of the document
5. Scope and content of the workcreation stages, contractors, deadlines
6. Development procedurea section new in 2020: how the system is built and evolves
7. Verification and acceptance proceduretest stages, who accepts, criteria
8. Preparing the site for commissioningwhat must be ready on the customer’s side
9. Documentation requirementsthe set of documents and formatting rules
10. Development sourcesthe documents the tech spec is based on

GOST 34.602-2020 is an interstate standard: adopted by the Interstate Council for Standardization (minutes No. 58 of 22 December 2020), and Uzbekistan voted for its adoption. Whether it is in force in a given country, check against the national register of standards. The standard requires requirements in the tech spec to be singular, consistent, up to date, feasible, verifiable and unambiguous.

User stories

In agile teams stakeholder requirements are written as user stories — short notes in the voice of a role. The role-feature-benefit template:

texta user story
As a support operator, I want to see the client’s enquiry historyso that I do not have to ask for the context again in every call.

The 3C model reminds us that a story is not a document: the card is a promise to talk, the conversation clarifies the details, and the confirmation is the acceptance criteria. A story’s quality is checked with the INVEST list: independent, negotiable, valuable, estimable, small, testable; if a story does not pass, reword it or split it.

Acceptance criteria are written in the Given-When-Then template — it structures the acceptance tests of a story:

gherkinan acceptance criterion of the password-reset story
# language: enFeature: Password reset  Scenario: the reset link has expired    Given a user is registered    When they open the reset-link email later than 60 minutes    Then the link does not work and issuing a new one is offered

The minimal set of criteria for password reset: a fresh link works and changes the password; a link older than 60 minutes does not work; someone else’s link does not change the password.

Non-functional requirements

Non-functional requirements (NFR) answer not “what does the system do” but “how well does it do it”: performance, availability, security, maintainability. An NFR without a number and a way to check it is not a requirement but a wish:

BadGood
the system must be fast95% of search requests — under 300 ms at 200 requests per second
the system must be reliableavailability 99.9% per month, failures do not corrupt data
protection of personal datapasswords stored only as hashes, access to records — logged
updates without downtimethe new version is installed without stopping, rollback — within 10 minutes

Every NFR has two mandatory elements: a metric with a number and a way to check it — a load test, a calculation from logs, a configuration audit. Architecturally significant NFRs are covered in the software-architecture reference, section “Quality attributes and non-functional requirements”.

What makes a requirement good

29148 lists the characteristics of a requirement, among them: necessary, unambiguous, singular, feasible and verifiable. The check: think of a test that fails the system when the requirement is not met — if there is no test, there is no requirement. The pairs below are the same rule on examples; take the search metric from the NFR above.

BadGood
the system must be convenient for managersa manager finds an order by its number in 3 clicks
search is fast and gives suggestionssearch takes up to 2 s and a separate requirement covers suggestions
it is desirable to support exportCSV export is included in the delivery or the requirement is removed

Business processes and BPMN

The analyst draws the as-is and to-be business process models in the BPMN 2.0.2 notation (Business Process Model and Notation, OMG) — the international standard ISO/IEC 19510 for business process diagrams. The diagram goes into the BRD or the tech spec as an appendix; requirements are stated in text — a diagram is not a verifiable requirement.

Traceability

Traceability links the levels: from a business requirement you can see which system requirements implement it, from a system requirement — which tests check it. A table is enough:

Business requirementSystemTest caseStatus
BR-1: a request in 1 daySR-12: automatic document checksTC-401passed
BR-1: a request in 1 daySR-13: assignment queueTC-402passed
BR-2: the client sees the statusSR-18: statuses by SMSTC-410failed
BR-2: the client sees the statusSR-19: personal account area—not covered

Why it is needed: an empty cell in the test column shows an unchecked requirement, and forward tracing shows what a change breaks: editing BR-1 affects SR-12, SR-13 and the tests TC-401, TC-402. Test-case technique is covered in the “Test design” reference, section “Test cases and defect reports”; how requirement changes are handled is in the section “Risks and changes”.

Section sources

the section is written from these pages

Design documents

Design documents capture the decisions taken between the requirements and acceptance: solution options, the system’s structure, the verification plan. In the GOST 34 complex, the types and completeness of documents are set by GOST 34.201-2020, and the content requirements by GOST R 59795-2021.

GOST R 59793-2021 defines the stages of system development: requirements gathering, concept development, technical specification, preliminary design, technical design, working documentation, commissioning, maintenance. Each stage has its own set of documents — from the concept to the acceptance certificate.

Each document builds on the previous one, and the test programme checks compliance with the tech spec before the certificate is signed.

Concept

The concept is the document of the “Concept development” stage: solution options, their evaluation and the choice among them. It is written before the tech spec: first the question “what are we building and why exactly this way” is answered, then the choice is fixed in the requirements. For the tech spec in detail, see the section “Requirements and specifications”.

HLD and LLD

DocumentWhat it describesWho reads itClosest GOST 34 counterpart
HLD — high-level designsystem components, integrations between them, deploymentarchitect, project manager, customerpreliminary and technical design
LLD — low-level designmodules, APIs, data schemasdevelopers, testerstechnical design, working documentation

Both levels are covered by one standard — IEEE 1016-2009: the software design description applies both to high-level and to detailed design; in the IEEE registry the 2009 edition is listed as inactive and retained in reserve (Inactive‑Reserved). Architectural views and C4 diagrams — in the “Software architecture” reference, section “Architecture description: C4, arc42 and ADR”.

ADR: decision log

An architecture decision record (ADR) is a short document devoted to a single decision: context, options, decision, consequences. It is written by whoever makes the decision — usually an architect or a lead developer; form matters more than length:

textadr/0007-database.md
# ADR-7: we choose PostgreSQL over MongoDBContext: the reports join dozens of entities; we need joins and transactions.Options: PostgreSQL, MongoDB.Decision: PostgreSQL — relational data and reports in SQL.Consequences: the schema is kept in migrations, reports are written in SQL.

The ADRs together form a decision log: an entry is not rewritten retroactively — a new decision supersedes an old one in a separate entry. Six months later the log makes it possible to reconstruct why the system is built exactly this way.

Test programme and specification

The test programme and specification records what is checked, how, against which criteria the system is accepted, and which protocol the result is documented with. Under GOST R 59792-2021, testing is carried out at the “Commissioning” stage and checks the system against the requirements of the tech spec.

TestingWhat is checked
Componentparts of the system, as they become ready for trial operation
Integrationinterconnected parts and the system as a whole
Preliminarythe system’s readiness for trial operation
Trial operationhow the system and the staff work in real conditions
Acceptancecompliance with the tech spec and the acceptance decision

For the techniques of composing checks, see the “Test design” reference, section “Test cases and defect reports”.

Operations documentation

The set under GOST 34.201-2020 also includes documents for operations — they are prepared for commissioning, not afterwards:

  • user guide — how to work with the system
  • administrator guide — how to configure and maintain it
  • process description — how the system fits into the organisation’s work

Who writes and who approves

The exact division of roles is fixed in the contract and the project charter; the typical picture is this:

DocumentWritten byReviewed byApproved by
Conceptanalystarchitect, sponsorcustomer
Tech specanalystcontractorcustomer
HLDarchitectdevelopment teamcustomer
LLDdevelopersarchitecttechnical lead
Test programmetest engineercontractor and customercustomer
Acceptance certificatecommissioncontractorboth parties

In an agile project the documents live in a wiki and a repository and change as work goes on, but the ADR log and the test programme remain there too, if acceptance is carried out under the contract: the decisions must be reconstructable and the acceptance verifiable.

Section sources

the section is written from these pages

Estimating and planning

A plan is the scope of work, its estimates, dependencies and buffers. Together they add up to a schedule that answers “when and at the expense of what”, not “when we would like it”. A schedule without dependencies and buffers is a wish list: it falls apart at the first delay.

Work breakdown: the WBS

The scope of work is held by a work breakdown structure (WBS): the project is divided into deliverables, and the deliverables into work packages. It is built around deliverables, not activities: a branch is named “Catalogue”, not “developing the catalogue”. The bottom level is the work packages: each one can be assigned to an owner, estimated and accepted separately.

textWBS of an online shop, three levels
1. Online shop├─ 1.1 Storefront│  ├─ 1.1.1 Catalogue and search│  ├─ 1.1.2 Product page│  └─ 1.1.3 Cart├─ 1.2 Orders and payment│  ├─ 1.2.1 Payment gateway│  └─ 1.2.2 Customer account├─ 1.3 Shop administration│  └─ 1.3.1 Admin panel└─ 1.4 Project management   └─ 1.4.1 Plan and acceptance

The 100% rule: the children add up to exactly the parent — no more and no less (this is how the GAO Cost Guide puts it). The structure exposes gaps and duplicates before the start, not in the middle of the project. Project management here is a branch in its own right, not an invisible background. It is also the frame of the schedule: every item of the plan leads to an element of the structure.

Four estimating methods

MethodWhen to useWhat you needExample
Expert judgementno data on similar workan expert who has done this kind of thing“the migration will take about three days”
Analogousa similar completed project existsits actual figures, adjusted for the differences“the catalogue took 20 days, this one is simpler — 15”
Parametricmeasurable volume and statisticshistorical data, a norm per unit“24 screens at 2 days each = 48 days”
Bottom-upwork broken into packagesthe WBS and estimates for every package“the total of 32 packages = 4.5 months”

Get the estimate from the people doing the work: they know the pitfalls, a directive from above does not. Back the estimate with a rationale — what is allowed for and where the numbers come from. Then a delay review relies on assumptions instead of hunting for someone to blame.

Three-point estimating and PERT

For risky items take three estimates: an optimistic O — if things go well, a most likely M and a pessimistic P — if they go badly. The PERT technique (Program Evaluation and Review Technique) weighs them in favour of the likely: E = (O + 4M + P) / 6. The spread is shown by the standard deviation σ = (P - O) / 6: the wider the range, the less trust a single estimate deserves. M alone hides the tail: the pessimistic scenario does not go away, and it has to be either accounted for or covered by a buffer.

Example: acceptance testing of the cart. O = 4, M = 6, P = 14 days. Expectation: E = (4 + 4·6 + 14) / 6 = 7 days, deviation σ = (14 - 4) / 6 ≈ 1.7 days. For comparison, the triangular mean (O + M + P) / 3 = 8 days: the NASA Schedule Management Handbook gives the same figure as the expected duration. Both formulas account for the tail, so both are above the naive M = 6; pick one and apply it to every item in the same way.

Story points and velocity

Agile teams size the same work in story points: a measure of relative complexity, not hours. An 8-point task is roughly twice as heavy as a 4-point one. The forecast comes from the team’s velocity — how many points it clears per sprint: a backlog of 120 points at a velocity of 30 points per sprint is 4 sprints. Converting points into hours is a mistake: being dimensionless keeps the estimate free of the status of a hard commitment; bring the hours back and you bring back the old argument about deadlines.

The Gantt chart

The Gantt chart is the familiar view of a schedule: activities in rows, dates across the top, each bar spanning an activity’s duration. Dependencies are shown as arrows between the bars, milestones as zero-duration points that consume nothing and mark major events: sign-off, acceptance, launch. Baseline dates sit next to the forecast ones, so slippage shows at once.

What the Gantt chart does not show. Resources: the critical path method treats performers as unlimited, and overloads are levelled separately. Nor uncertainty: a bar answers “when, if all goes well”, not “with what probability”. The chance of hitting the deadline is what schedule risk analysis shows: Monte Carlo simulation runs the network many times, drawing durations from ranges, and produces a distribution of finish dates.

Critical path: the calculation

The critical path is the longest chain of dependent activities: its total duration is what sets the project deadline. Activities on the path have zero total float: a one-day slip moves the finish by a day. For the other activities, float shows how many days they can slip without consequences.

Durations in days; early and late start windows are in the table below.

The numbers for the network come from two passes. The forward pass runs left to right and computes early dates; the backward pass runs back from the finish and computes late ones: the latest day an activity can wait without moving the end of the project. Late minus early start gives the total float; counting starts at day zero, the project start.

ActivityDuration, daysStart window, early–lateTotal float
A30–00
B43–63
C53–30
D47–103
E68–80
F414–140

Activities B and D can slip by 3 days: their branch is shorter than the critical one by exactly that much. Crashing B or D will not bring delivery forward by a single day — the branch A → C → E → F is what holds the deadline. Only activities on the critical path are worth speeding up.

Buffers as separate lines

Spare time hidden inside every task (“two extra days just in case”) works against the plan: Parkinson’s law inflates every estimate, and the manager loses sight of where the project actually has time. The critical chain method gathers the safe time out of the individual activities and places it as one buffer at the end of the chain: a common reserve handles risks better than a scattering across tasks.

There are two kinds of reserve, and they have different owners. Contingency covers identified risks: its size comes out of schedule risk analysis — for example, as the gap between the planned date and the 80% confidence date. It sits as a separate activity before the finish milestone and is spent through change control. Management reserve is a store for what nobody foresaw: the project manager holds it and does not hand it out to teams. Neither is the same as float: float arises on its own from the logic of the network, while the reserves are planned deliberately.

The roadmap

The roadmap is one level above the schedule: goals and major outcomes by quarter, without detailed dates. Distant items are deliberately left coarse: under rolling wave planning only the near zone, where information is reliable, is planned in detail. Far-off work, broken down too early, keeps being reworked. The difference is simple: the schedule is a commitment to an agreed scope, the roadmap is an order and landmarks that are refined as work moves on.

Section sources

the section is written from these pages

Scrum and Kanban

Scrum is a lightweight framework in which the team works in short sprints and every sprint releases an increment — a working part of the product. Kanban is a strategy for optimising the flow of value: work items move across a board with a WIP limit and no sprints. Both approaches rest on transparency, inspection and adaptation.

Scrum defines three accountabilities, five events and three artifacts — none may be left out and none may be added. Kanban sets its minimum stricter: three practices and four flow metrics. The choice depends on what matters more to the team — a fixed rhythm or a continuous flow.

The three Scrum accountabilities

The basic unit of Scrum is a team of up to ten people with no subteams or hierarchies: it is cross-functional and decides for itself who does what and when. The work is set by the Product Owner through the Product Backlog.

AccountabilityResponsible for
Developerscreate the plan for the sprint — the Sprint Backlog, build the increment and hold each other accountable as professionals
Product Ownermaximises the value of the product: manages the backlog and states the product goal explicitly
Scrum Masteris accountable for the team’s effectiveness: helps everyone understand Scrum, removes impediments and keeps the events time-boxed

The Product Owner and the Scrum Master are one person per accountability; there is a single Product Owner, not a committee: only they may change the backlog, everyone else convinces them.

The five events

The sprint is a container for the other events: a period of no more than one month, and a new one starts immediately after the previous sprint ends. During a sprint the team does not take on changes that endanger the goal and does not lower quality; the scope is clarified and renegotiated with the Product Owner.

EventTime-boxOutcome
Sprintone month or lessthe increment; the sprint goal does not change
Sprint Planningup to 8 hoursthe sprint goal, the selected items and the plan
Daily Scrum15 minutesthe plan for the next working day
Sprint Reviewup to 4 hoursthe result is shown to stakeholders; the backlog may change
Sprint Retrospectiveup to 3 hoursa plan of improvements; the most important ones are applied right away

Inspection and adaptation are built into every event: the Daily Scrum checks progress against the sprint goal, the review checks the result against the product goal, and the retrospective checks the way the team works itself.

The event time-boxes are for a one-month sprint.

Artifacts and their commitments

Each artifact is bound by a commitment that makes it transparent: everyone who looks at the artifact sees the same thing.

ArtifactCommitment
Product Backlogthe product goal
Sprint Backlogthe sprint goal
Incrementthe Definition of Done

The Product Backlog is the single source of work for the team: the Product Owner orders and refines it as needed, and the Developers estimate the size of the items. The Sprint Backlog is the Developers’ plan: the goal, the selected items and the plan for delivering the increment.

The Definition of Done is a formal description of the state the increment must reach to satisfy the quality measures. For a web application this could mean: the code has been reviewed by a second developer, the automated tests have passed, the documentation is up to date, the change has been deployed to a test environment and the acceptance criteria are met. An item that does not meet the Definition of Done cannot be shown at the review — it goes back to the backlog.

Team velocity

Velocity is a measurement after the fact: how many user story points the team completed in a sprint. The example from the Agile Alliance glossary: stories worth 2, 2 and 3 points are planned; the first two are done and the third is 80% complete. Only 100% counts as done, so the sprint velocity is 4 points; the unfinished story does not count and is completed in the next sprint.

  • Velocity is not a forecast or a budget: you cannot “set the velocity”.
  • Only the velocity of the team as a whole exists; there is no such thing as “individual velocity”.
  • Comparing the velocity of different teams is meaningless: they estimate in different ways.
  • A story that repeatedly fails to reach done is a signal to split stories.

Kanban practices

Kanban is not tied to any industry or scale; value is optimised by balancing effectiveness, efficiency and predictability. The three practices work in combination:

  • define and visualise the workflow — the Definition of Workflow agreement: the work items, the start and end points, the states and the rules of the flow;
  • actively manage the items — keep WIP under control, keep items from ageing, unblock the stuck ones;
  • improve the flow — continually, without waiting for formal meetings.

Explicitly limiting WIP (work in progress) makes the system a pull system: a new task is taken on only when there is spare capacity. On the board this is a column limit: no more than 3 cards in “In progress”; the fourth is not taken until a slot frees up.

The four flow metrics

MetricWhat it measures
WIPthe number of items started but not finished
Throughputthe number of items finished per unit of time
Work item agethe time from the start of work on an item to the current day
Cycle timethe time from the start of work on an item to its completion

The service level expectation (SLE) is a forecast expressed as a duration and a probability. The example from the Kanban Guide: “85% of work items will be finished in 8 days or less”. Until historical data is available, an educated guess will do.

Little’s law

Little’s law relates the average number of items in a system (L), the rate at which they arrive (λ) and the average time (W): L = λW. For a flow of tasks: average cycle time = WIP / throughput. With 12 tasks in progress and 4 finished per day, the average task takes 3 days. What makes the flow faster is a smaller WIP, not the speed of each task.

Scrum and Kanban side by side

AspectScrumKanban
Rhythmsprints of a fixed lengtha continuous flow
RolesProduct Owner, Scrum Master, Developersno mandatory roles
Changes during the workare taken into the next sprintjoin the flow at any time
Key metricsvelocity; an increment every sprintWIP, throughput, cycle time, work item age
When it fitscomplex work organised around a sprint goalan unpredictable flow: support, operations

The approaches do not compete: teams work in sprints and at the same time keep a board with WIP limits. How to present flow metrics to management — see the section “Metrics and reporting”.

Section sources

the section is written from these pages

Roles and responsibilities

A role in a project is a set of duties and decision areas, not a line on an org chart. One person may hold several roles, but every decision has one owner: where two people answer for a decision, nobody makes it.

Project manager and product manager

Both roles shorten to PM (project manager and product manager), which is why they get confused. The difference is the question each one answers: the project manager answers “how do we deliver on time and on budget”, the product manager answers “what are we building and why”. In a small team one person may hold both roles, but the decisions stay separate: schedule and budget are one thing, the make-up of the product is another.

QuestionProject managerProduct manager
Goaldeliver the project on time and on budgetgrow the product around users’ needs and the organisation’s priorities
Horizonthe project itself: from start to acceptancethe product life cycle: years
Measure of successscope, schedule, budget, qualityhow useful the product is: users’ needs, the organisation’s goals
Reports tothe project sponsor, on schedule and budgetthe business owner, on the value the product delivers

Product Owner and Scrum Master

Scrum fixes three accountabilities in the team: Developers, the Product Owner and the Scrum Master. These are accountabilities, not job titles. There is one Product Owner, and they answer for the value of the product: they set the goal and keep the backlog in order. The Scrum Master answers for the team’s effectiveness: they help everyone understand Scrum and get impediments removed. A Scrum team is not split into subteams and has no hierarchy.

Business analyst and systems analyst

Both roles are called “analysts”, but they answer different questions: the business analyst (BA) answers “why”, the systems analyst (SA) answers “how”. A BA finds out how processes work and what the business needs, and turns this into documents: business requirements (a BRD, Business Requirements Document), process models in BPMN (Business Process Model and Notation), user stories. An SA takes ready requirements and answers how the system will meet them: data, integrations, behaviour. Their documents are a Software Requirements Specification (SRS) and specifications for integrations and APIs.

RoleWhat they find outWhat documents they write
Business analyst (BA)how the business processes work and what the business needsa BRD, process models in BPMN, user stories
Systems analyst (SA)how the system will meet the requirements: data, integrations, behaviouran SRS, specifications for integrations and APIs

The business analysis body of knowledge BABOK (IIBA) describes this work as six knowledge areas: business analysis planning and monitoring, elicitation and collaboration, requirements life cycle management, strategy analysis, requirements analysis and design definition, and solution evaluation.

Architect, tech lead, QA, delivery manager

The roles most often confused with the project manager, one phrase each:

  • The architect — answers for technical decisions: platform, integrations, and the reliability and security of the system as a whole.
  • The tech lead — answers for the technical quality of the code and the work of the development team.
  • The QA engineer — answers for checking that the system meets the requirements; quality as a whole is the whole team’s responsibility.
  • The delivery manager — answers for the process: organises the team’s work so that it moves on its own, and clears impediments.

Stakeholders

Stakeholders are everyone who influences the project or depends on its result: the sponsor, users, neighbouring departments, the regulator. Their interests and influence are collected in a register. The register is a living document: interests change as the project goes on, so it is reread at every major stage.

WhoInterestInfluenceHow we engage them
The business sponsorthat the CRM pays for itself on timehigha meeting every two weeks, decisions about money
The bank’s IT directorthat the system passes the information security audithighapproving the architecture and access rights before development
The security teamthat customer data does not leakhighreviewing the security requirements before development
Branch managersthat the managers find the system convenient to work inmediuma demo every month, collecting feedback
Call-centre operatorsthat calls are handled fasterlowa survey after the demo, work with the pilot

The RACI responsibility matrix

A responsibility matrix (RACI) is a table with the work in rows and the roles in columns. The letters mean: R (responsible) — does the work; A (accountable) — answers for the result and makes the decision; C (consulted) — gives advice; I (informed) — is told about the result. There is one rule: exactly one A per row. The example is a CRM project at a bank, five pieces of work and five roles: approve the technical specification, approve the architecture document (HLD, high-level design), release a version, accept the work, change the budget.

WorkSponsorProject managerProduct OwnerArchitectTech lead
Approve the specificationARCCI
Approve the HLDARICI
Release a versionIAICR
Accept the workICA/RII
Change the budgetARCII

Conway’s law

Melvin Conway formulated Conway’s law in 1968: an organisation that designs a system will produce a design whose structure mirrors that organisation’s communication structure. If three teams that barely talk to each other work on one system, the system breaks into three loosely coupled modules, one per team. Fred Brooks fixed the name “law” in the book The Mythical Man-Month. The lesson for planning: split the teams along the future architecture’s boundaries. The communication structure that has already taken shape will impose its own on the system anyway, so team boundaries are chosen before development, together with the architecture.

More on this

A tester’s work and acceptance are covered in the test-design reference, section “Basic concepts of testing”; architectural decisions in the software-architecture reference. The Scrum team is covered by the section “Scrum and Kanban”, the technical specification by the section “Requirements and the technical specification” of this reference.

Section sources

the section is written from these pages

Risks and changes

A risk is an uncertain event that will affect the project’s objectives if it happens; an issue is something that has already happened and calls for a response. Risks are kept in a register, and changes to the scope are accepted through a change request.

The whole team looks for risks from the project’s first days: every new fact is checked for probability and impact, and a response and an owner are assigned. A missed risk does not disappear — it turns into an issue, and an issue costs more to resolve.

Risk register

A risk register is a table where every risk has a score and an owner. Probability and impact are scored on a scale from 1 to 5; their product gives the risk score and sets the order in which risks are handled.

RiskProbability (1–5)Impact (1–5)ScoreResponseOwnerDeadline
The only integration developer leaves3515reduce: a second person reviews the code, documentation for the integrationproject managerby the end of sprint 2
Delay in the partner bank’s API4416transfer: the testing deadline goes to the partner under the contractdevelopment leadbefore the contract is signed
A new requirement from the regulator2510accept: a 10% time reserve in the planproject managerreviewed every month

A score of 1–5 is low, 6–12 medium, 15–25 high. High risks are discussed every week, medium ones every two weeks, low ones when the register is reviewed; the register itself is reviewed regularly. A row without an owner and a deadline is not a risk but a note in the margin.

Impact ↓ / Probability →12345
5 (critical)510152025
4 (severe)48121620
3 (moderate)3691215
2 (minor)246810
1 (minimal)12345

Response strategies

Handling a risk means choosing a risk response strategy and carrying it out:

  • avoid — remove the source itself: do not build the integration with an unreliable supplier
  • reduce — lower the probability or the impact: code review by a second person, a reserve in the plan
  • transfer — hand part of the risk to another party: a penalty for missing the deadline in the contract
  • accept — deliberately keep the risk, building in a reserve of time or money

The choice balances the cost of the response against the size of the risk. A risk that has materialised is no longer a risk: it moves to the issue log, and the owner switches to the response plan.

Change request

A change to the scope is accepted through a change request: what is being changed and why, the impact on scope, schedule and cost, the decision and who made it. There is no such thing as a verbal “let’s just add a few small tweaks” — every tweak goes through a request. Under GOST 34.602-2020, changes to the technical specification are made by a supplement, and a supplement goes through the same approval procedure as the tech spec itself.

textchange request
change request: add CSV export of reportsreason: the accounting department exports the data by handimpact on scope: +2 items in the backlogimpact on schedule: release 1.4 moves back by 3 daysimpact on cost: no changedecision: accepted by the Product Owner on 12 March 2026

An accepted request changes the baseline: the scope, schedule and cost in the plan. A deviation from the new baseline is again counted through a request — that is how the accounting closes the loop.

Scope creep

Scope creep is a gradual growth of scope without change requests. The signs: a sprint is “slightly overfull” for the second time in a row, and the backlog grows faster than the team’s velocity. Example: “add one more filter to the report” — estimated at 4 hours, but in reality a change of the reporting library and a swallowed sprint. The defence is a scope baseline and a mandatory change request.

RAID log

A RAID log gathers four project lists into one table: risks, assumptions, issues, dependencies — and it is reviewed together with the register at one meeting. One example for each letter:

CategoryExampleWhat is done
riskthe only integration developer leavingowner and response strategy in the register
assumptionthe partner bank will open a test environment before 1 Marchchecked; if false, it becomes a risk
issuethe test environment was opened on 12 Marchissue log: owner and resolution deadline
dependencythe release of the registration form is waiting for the password migrationkept visible to both teams

Technical debt as a risk

Technical debt is Ward Cunningham’s metaphor as Martin Fowler presents it: flaws in the internal quality of code slow down future work, the way interest slows the repayment of a debt. With a clear module structure a new feature takes 4 days; with a cluttered one, 6 — and the difference of 2 days is the interest on the debt. A one-off refactoring pays off when several similar changes still lie ahead.

Debt enters the register as an ordinary risk: probability — the next rework of the module, impact — the extra days, owner — a person, repayment plan — reworking it in portions across ordinary sprints. Debt in a stable part of the system that will not need changing can be accepted without repayment.

After launch: changes and incidents in ITSM

After launch the rules change: the service is run by IT service management (ITSM) — a discipline and a library of ITIL practices.

Change enablement assesses the risk of a change and authorises it. A change advisory board (CAB) is convened before risky changes; standard changes — recurring and pre-approved ones — do not need the CAB.

An incident is a failure or a degradation of the service: the goal is to restore the service quickly. A problem is the cause of one or more incidents: the goal is to find it and remove it. The single point of contact for users is the service desk. The configuration management database (CMDB) shows what a change will affect.

In the projectIn operation
change requestchange (RFC)
project issueincident
risk registerproblem management

The requirements for a service management system are set by ISO/IEC 20000-1:2018 — the third edition, confirmed in 2023, with Amendment 1:2024 on climate action. Related sections — “Procurement and contracts”, “Metrics and reporting” and “Standards and bodies of knowledge”.

Section sources

the section is written from these pages

Procurement and contracts

Procurement runs from market research to a signed acceptance certificate. The choice of contract type distributes risk between the customer and the contractor: a fixed price shifts the risk to the contractor, Time & Materials — to the customer.

The procurement path is the same for a private and a public customer: first the market is explored, then proposals are requested and a contract is signed that fixes the scope, the price, the service level and the acceptance procedure.

Requests to contractors

Requests are sent before a contractor is chosen: this is how the market is explored and comparable answers are obtained instead of random presentations.

RequestWhat it is forIs the reply bindingExample
RFI — request for informationto learn the market and its capabilitiesno: the reply is not an offer and creates no contract“what time-tracking solutions are there?”
RFP — request for proposalsto state the requirements and the evaluation criteria, and receive proposalsyes: the reply is an offer, and acceptance creates a contract“build system X; the evaluation criteria are in the documentation”
RFQ — request for quotationsto get a price for a scope that is clear in advancenot until acceptance: the reply is a quotation, not an offer“lay out 20 pages from a mock-up — name your price”

The evaluation criteria are announced in advance, in the documentation itself — only then are the proposals comparable and the choice explainable: experience and references, the team, the work plan, the price and the support terms.

Contract type

A fixed-price contract is concluded when the risk is minimal or predictable: the scope, the requirements and the deadlines are understood and written down. The contractor builds reserves into the price and makes a profit on the savings.

TypeWho carries the riskWhen it fitsWhat makes it risky
Fixed Pricethe contractorthe scope is clear and predictable, the requirements are written down in the technical specificationreserves are built into the price; every change to the scope goes through a change request
Time & Materials (T&M)the customerthe scope cannot be estimated in advance: research, support, developmentthe cost grows without a ceiling; there is no incentive to work faster

A T&M contract is billed not by scope but by hours: the hourly rate covers salaries, overheads and profit, and materials are charged as actually used. Such a contract is used only when the scope and the deadline cannot be estimated in advance with reasonable accuracy. Once experience has been gained and the price has become predictable, T&M should not be dragged out — the parties move to a fixed price.

textsample T&M calculation, amounts in conventional units
team:        3 developershour pool:   3 × 160 h = 480 h per monthrate:        150 c.u. per hour, overheads includedT&M month:   480 h × 150 = 72,000 c.u.ceiling:     216,000 c.u. — 3 months of work

Public procurement in Uzbekistan

Public procurement in Uzbekistan is governed by the law “On public procurement” (ZRU-684). The main procedures are the electronic shop, a descending-price auction, best-offer selection and the tender; splitting a purchase into parts in order to avoid a competitive procedure is prohibited by the law.

What to put in the SOW

The statement of work (SOW) is an appendix to the contract in which the scope is fixed in words that allow judging completion. In projects under GOST 34.602-2020 the scope rests on the technical specification with verifiable and unambiguous requirements.

  • the purpose and background of the procurement
  • scope: what we do and what we do not do
  • deliverables — named one by one
  • deadlines and stages
  • acceptance criteria for each deliverable
  • assumptions: what we take to be true for the estimate to hold
  • dependencies on the customer: data, access, decisions
  • change procedure: how the scope and the price change

“What is not included” is written as precisely as “what is included” — otherwise “small tweaks” will eat both the deadline and the budget. How a change is formalised — see the section “Risks and changes”.

SLA and OLA

A service level agreement (SLA) is part of a support or operations contract in which quality is set by numbers that can be verified.

MetricWhat it coversExample
Availabilitythe share of time the service is up; measured per month99.5% per month: 0.5% of 30 days is 3.6 hours
Response timehow many minutes are allowed for the first reply to a ticket15 minutes for the critical priority
Resolution timehow much time is allowed for the fix4 hours for the critical priority
Maintenance windowwhen work affecting the service may be carried outSaturday 02:00–06:00 Tashkent time

An operational level agreement (OLA) is the same kind of level agreement, but between internal teams: they commit to each other with the same numbers so that the external SLA adds up. If the network team’s OLA promises 4 hours and the external SLA is 1 hour, the external contract is broken. How availability is calculated is covered in the reference “Infrastructure and cloud architecture”.

NDA

A non-disclosure agreement (NDA) defines which customer data must not be handed to third parties and what counts as a breach. An NDA is signed before the contractor is sent an RFP with internal data or given access to the systems: once information is disclosed, it cannot be taken back.

Acceptance of the work

The work is accepted not by a manager’s eye but by tests carried out under the test programme and methodology: what to check, how, and against which criteria. The result is a protocol; defects are logged with a deadline for fixing them and the tests are repeated.

After tests without defects, or after rework, the parties sign the delivery and acceptance certificate. The contract states the time allowed for checking and for raising defects, and what missing that deadline means: whether the customer’s silence counts as acceptance. Who writes and who approves the test programme and the certificate — see the section “Design documents”.

Outsourcing and outstaffing

ModelWho manages the peopleWho answers for the resultCustomer’s risks
Outsourcingthe contractorthe contractor — under the SLAdependence on the contractor; a difficult handover to the next contractor
Outstaffingthe customer — assigns tasks to the dedicated peoplethe customer — for the result of their workthe people are not in-house staff: knowledge leaves with them; risk if the setup is not properly formalised
In-house hiringthe customerthe customermore expensive on a short project; hard to resize the team quickly

In Uzbekistan, contractors with IT Park resident status have tax benefits: income tax of 7.5%, corporate tax and the single social payment at 0%. The rates are checked on the official residents page on the date the contract is signed.

Section sources

the section is written from these pages

Project economics

A business case is a document that answers two questions: why the project is needed and whether it will pay off. Project economics is worked out before the start and recalculated at each phase, and an MVP, a prototype and a pilot are ways to test the numbers cheaply before investing in the full product.

The business case: five sections

In the Five Case Model, which HM Treasury teaches for writing business cases, the justification is assembled from five sections. Each answers its own question — omitting any one leaves a blind spot in the decision:

SectionQuestion
StrategicWhy the project? What happens if it is not done?
EconomicWhich of the realistic options gives the best ratio of benefits to costs?
CommercialWho to sign the contract with, and on what terms the market will allow it?
FinancialWhat will we pay with, and can the budget carry the project?
ManagementWho will see the work through, and how?

The sections depend on each other: the strategic case determines which options are compared at all, the economic case picks the preferred one from them, and the financial case shows its price. The project is worth continuing while all five answers still hold.

Whole life cost

Whole life cost is every cost from the start of development to the end of the system’s life: development, licences, infrastructure, support and decommissioning. Options should be compared on it, not on the price of the first year: an option with a high starting price may turn out cheaper thanks to low running and decommissioning costs.

CostOption A, thousand monetary unitsOption B, thousand monetary units
Development, 2026–2027600800
Licences and cloud, per year20080
Support, per year100120
Decommissioning5020
Total over 3 years15501420

Option A is cheaper at the start but more expensive over three years: expensive licences and cloud outweigh the difference in development. The first year is always deceptive — when comparing options, look at the whole period for which you promise to support the system.

CAPEX and OPEX

Costs fall into capital expenditure (CAPEX) and operating expenditure (OPEX). Capital costs are one-off and create an asset; operating costs recur for as long as the system runs. The division matters for the budget: capital costs are requested separately and once, while operating costs are built into the annual budget.

CostCAPEX or OPEXWhy
Server purchaseCAPEXA one-off purchase of an asset with a service life
Cloud subscriptionOPEXA payment for a service while it is needed
In-house system developmentCAPEXDevelopment-phase costs can become an intangible asset under IAS 38
Research and prototypesOPEXAn expense of the research period; it creates no asset
Support team salariesOPEXRecurs while the system runs

Payback

The simplest measure of payback is return on investment, ROI. If a project costs 600 thousand monetary units and brings 300 thousand of benefit a year, over three years the benefit is 900 thousand, and ROI equals (900 − 600) / 600 × 100% = 50%. The simple payback period is 600 / 300 = 2 years.

Money from different years is not equal: a million in three years is worth less than a million today. The discounted payback period and NPV (net present value) count the same flows with the value of future years reduced — they come into play when a financier makes the money decision.

Adjusting for optimism bias

In reality, costs and timelines are almost always higher, and benefits lower, than in the original business case — this systematic error is called optimism bias. HM Treasury requires it to be allowed for explicitly: cost and timeline estimates are raised and the benefit estimate is lowered even before approval.

In practice, the adjustment is budgeted as a separate line or as a range: a margin is added to the timeline and cost estimates from the section “Estimation and planning”, benefits are brought down to realistic ones, and the adjustment shrinks as the data is refined. A business case without the adjustment is not economics but wishful thinking.

PoC, prototype, MVP and pilot

Before paying for a full product, the idea is tested in small formats. They answer different questions, and confusing them is costly: products built on untested assumptions end up unused.

WhatWhich question it answersWho uses itHow it endsExample
PoCIs it technically possible?developersa conclusion: possible or nota request to the bank’s API from a script
PrototypeWhich assumptions are the riskiest, and do they hold?the team and users in testsa list of tested ideasa screen mock-up in Figma used to test tasks
MVPDo users need the product?early usersmetrics and a decision: persevere or pivota shop with a single storefront and payment
PilotDoes the solution work in real conditions?part of the real usersa report and a deployment decisionone warehouse of a retail chain on the new software

An MVP is a minimum viable product: a version that is already used to learn from. The core is the build–measure–learn loop from The Lean Startup: the idea is turned into a product, user reaction is measured, and the team decides whether to persevere or pivot. A prototype, by contrast, tests the riskiest assumptions before development even starts, and its code is usually thrown away after the test.

Stop criterion

A stop criterion is a condition, written down in advance, under which the project or the test is closed. It is fixed before the start, while no one has yet invested effort it would be awkward to answer for. For a warehouse pilot, the criterion might look like this:

textan entry in the business case
Pilot closure conditions:  deadline: by 30 June 2027;  continue if: the share of orders picked without errors is ≥ 98%    and the average picking time is ≤ 12 minutes;  close if: the ERP integration has not gone live by 1 April    or the error rate has been ≥ 5% for two weeks in a row.

The conditions make stopping a decision taken in advance rather than a defeat admitted under pressure of circumstances. For the metrics used to judge a project’s progress, see the section “Metrics and reporting”.

Section sources

the section is written from these pages

Metrics and reporting

Progress is shown by progress metrics — schedule, budget and scope; business value is shown by outcome metrics. Neither works without the other: a chart can lead evenly to a result nobody needs, and a useful product can miss the dates because nobody measures progress.

KPIs and OKRs

A KPI (key performance indicator) is a constant health indicator: it shows whether the process works. OKRs (objectives and key results) are a measure of change: an objective and 3–5 measurable key results per quarter.

WhatKPIOKR
Essencea constant indicator of the health of a process or a productan objective and 3–5 measurable key results
Horizonconstant, reviewed rarelya quarter, then a new set
Examplea customer request is handled in 4 hours“requests are resolved within an hour” — an objective for the quarter

An example of OKRs for the same support portal:

textOKRs for a quarter
Objective: the customer portal has become fast and reliableResult 1: 7 tickets out of 10 are closed within 1 hourResult 2: pages open within a second for 95% of customersResult 3: the share of releases rolled back is below 2%

The objective is set without numbers — it is a direction. The numbers live in the results: at the end of the cycle each result is either met or not, there are no grey answers. Google scores results on a scale from 0.0 to 1.0 and takes the average; a simpler way is “red, amber, green”. An easily met result is not an achievement: OKRs are meant to stretch the team.

The link is direct: result 1 moves the KPI “request handling time”. OKRs change the metric; KPIs watch that it does not slide back after the quarter.

Earned value

The earned value management (EVM) method reduces schedule and budget to a single set of numbers. Three quantities are taken on the same date. In the GAO Cost Guide the same quantities are called BCWS, BCWP and ACWP — the budgeted cost of work scheduled, the budgeted cost of work performed and the actual cost of work performed.

QuantityWhat it isIn the example
PV, planned valuethe budget of the work that was planned to be completed by the reporting date400,000 units
EV, earned valuethe budget of the work actually completed by that date300,000 units
AC, actual costwhat the same completed work actually cost360,000 units

Example: the project budget (BAC, budget at completion) is 1,000 thousand units; at the end of month 3, PV = 400, EV = 300, AC = 360. Four numbers come out of them: the cost variance CV = EV - AC = −60 and the schedule variance SV = EV - PV = −100; the indexes CPI = EV / AC ≈ 0.83 and SPI = EV / PV = 0.75. A CPI below one means the completed work costs more than planned; an SPI below one means less work has been completed than planned. GAO then advises looking for the causes at the level of WBS work packages rather than treating the project average.

The forecast of the total cost at completion (estimate at completion, EAC) extends the index over the rest of the project: EAC = BAC / CPI. In the example: 1,000 / 0.83 ≈ 1,200 thousand — an overrun of about 200 if the efficiency does not change. Without the indexes, the budget shares give the same signals: PV / BAC, EV / BAC, AC / BAC; if the spent share is noticeably ahead of the share of completed work, the budget is already leaking.

Burndown

A burndown is a chart with the remaining work on the vertical axis and time on the horizontal axis. There are two variants: a sprint burndown — the sprint’s remaining work by day, and a product burndown — the remaining backlog across sprints. The line drops when the team completes tasks; a flat stretch is visible from afar and pushes problems into the conversation sooner. Scrum does not require a burndown: it is not in the Scrum Guide, the required artefacts there are different.

A burndown does not show changes in scope: if tasks are added to the backlog mid-sprint, the line rises, and you cannot tell whether work has been added or the team has stalled. A burn-up shows the total backlog size as a separate line.

DORA metrics

The DORA metrics are five software delivery measures that DORA identified in its research; by its findings, they predict both the organisation’s results and the well-being of teams. Three measures add up to throughput — how many changes reach production; two add up to instability — how deployments go.

MetricWhat it measures
change lead timefrom a commit to the repository to release into production
deployment frequencythe number of deployments per period
failed deployment recovery timehow long it takes to repair a failed deployment
change fail ratethe share of deployments that required a rollback or an urgent fix
rework ratethe share of deployments done unplanned because of a production incident

The fourth metric used to be called MTTR (mean time to recovery); DORA now phrases it as the time to recover from a failed deployment. The metrics are measured for one application or service at a time: comparing teams across different systems is misleading, and the goal is improvement over time, not competition. A metric must not be declared a goal: “a deployment every day by the end of the year” is a way to get painted-on numbers — the team will start improving the metric rather than the delivery. All five metrics are kept shared between development and operations.

How to collect the DORA metrics from a pipeline — in the “CI/CD” reference. After the result is handed over to operations, the service’s progress is measured with IT service management (ITSM) metrics — the number of incidents, recovery time and SLA compliance; related places are the sections “Risks and changes” and “Procurement and contracts”.

A one-page status report

A status report is a page the sponsor reads in five minutes: status on schedule, budget and scope in green, amber or red; then what has been done, what is next, the risks and the decisions needed. The day and the format are set at the project start (see the section “Project start checklist”).

textthe frame of a weekly report
Customer portal — report for week 12Status: schedule — amber; budget, scope — greenDone: the bank integration has been acceptedNext: load tests and catalogue acceptanceRisks: bank API timeouts — medium, we are watchingDecisions: the bank’s test environment was down for 3 days,  we ask the sponsor to write to the partner by 14 November

Amber is not the midpoint between green and red: it means there is a deviation and the team is handling it itself. Red is set when the sponsor’s decision cannot be avoided, and no one waits for the scheduled reporting date. In the example the amber status has a cause and one decision with an addressee and a date. The budget status is checked against the earned value figures: 36% of the budget spent with 30% of the work completed — that is no longer green.

Where to look next: whether the project is worth its money — in the section “Project economics”; the team’s speed and flow metrics — in the section “Scrum and Kanban”; live dashboards of service metrics — in the “Prometheus and Grafana” reference.

Section sources

the section is written from these pages

Common mistakes in approach

Most IT project failures come not from technology but from decisions that nobody made, estimates turned into promises and blurred responsibility. Below are seven common mistakes: what each one leads to and how to fix it.

MistakeWhat it leads toThe right way
No decision ownerquestions hang for weeksone A in RACI, the Product Owner
An estimate as a commitmentfear of forecasts, drawn-out estimatesa range with a confidence level
Hidden requirementsrework at acceptancean NFR checklist from day one
Agile without ruleschaos instead of flexibilitya sprint goal, a Definition of Done
Reports instead of resultsa green status without a productmeasure completed increments
Ignoring technical debtevery rework costs morepart of the sprint goes to paying it down
The bus factorknowledge held by one personpair work, ADRs, rotation

No decision owner

A decision is “handed to a committee” — and hangs for weeks: everyone waits for somebody else to decide, and the meeting looks only at status instead of deciding. In the RACI matrix every decision has exactly one A (accountable) — the person answerable for the decision itself; consultation and execution are separate roles (see the section “Roles and responsibilities”).

In Scrum this role belongs to the Product Owner: they alone are answerable for the order of the Product Backlog and may delegate the work, but not the responsibility. The right way: for every type of decision it is written down who decides and by when; contested questions are brought to a single decision-making meeting.

Example: a bank is preparing a release with a new payment method. The question of the receipt format travels between the architecture committee and the customer for weeks — or the one person responsible for the payment core decides within a day, and the committee is merely informed.

An estimate as a commitment

The team is punished for a forecast that did not come true — so it takes ever longer to estimate and builds in padding. As early as the 2011 revision of the Scrum Guide it was made explicit: the Developers do not commit to completing the planned scope, they give a forecast that is refined as the sprint proceeds.

The right way: an estimate is given as a range with a confidence level — “about 3 weeks at 80% confidence” — and what is committed to is the sprint goal, not the scope of tasks. Relative estimates in story points defuse the tension between developers and managers: they compare relative complexity (“twice as heavy as that task”), not deadlines.

textan estimate in an md file
# estimate.md — a sprint estimate, not a commitmentSprint 42 (2 weeks): forecast at 60% of the usual scope # task groups: range and confidencebank integration          5–8 days, confidence 70%payment history screen       2–3 days, confidence 90%

Hidden requirements

At acceptance, non-functional requirements (NFR) and undescribed integrations surface: “what about load testing?”, “what about the export to the accounting system?”. Deadlines slip: the requirements existed only in people’s heads (see the section “Requirements and specifications”).

The right way: from the first day of the project a checklist of non-functional requirements is maintained — performance, availability, security, compatibility — together with a list of integrations and their owners on the other side. Every acceptance criterion is verifiable: not “the system must be fast”, but “the report page opens in 2 seconds with 100 users”.

Agile without rules

“We are agile — there is no plan”: sprints without a goal, “done” means something different to everyone, retrospectives cancelled as unnecessary. A couple of months later the work is going on, but there is no working product.

Agile is not a rejection of planning. Scrum requires a sprint goal, a shared Definition of Done and a retrospective at the end of every sprint, where the team decides what to change. The Agile Manifesto names working software as the primary measure of progress: if after two sprints there is none — the problem is not the method but its absence (see the section “Scrum and Kanban”).

Reports instead of results

The status in the report is green, “80% done”, and there is nothing to launch: effort has been absorbed, but there is no increment. “Nearly done” percentages are never checked, yet are shown willingly.

The right way: measure the outcome — completed increments and earned value: how much work has been accepted at plan prices as of today (see the section “Metrics and reporting”). A demonstration of the working product every 2 weeks is more truthful than any status: if there is nothing to show — the status is yellow.

Ignoring technical debt

Debt is accumulated for a year, and then every small rework costs more and more: these are the “interest” on technical debt — the extra effort of changing code already in production. The metaphor and the benefit calculation are in the section “Risks and changes”; here the point is a management mistake: the debt is invisible and unplanned for.

The right way: the debt is visible — items in the backlog and rows in the risk register with an impact assessment; part of the scope of every sprint, say 10–20%, is set aside for paying it down. Priority goes by the frequency of change: in frequently changed areas of the code the debt is paid off at once, abandoned modules can wait.

The bus factor

One person knows the bank integration: they go on holiday — the integration stops. The bus factor is how many people have to be hit by a bus for the project to stall. A factor of 1 is the riskiest configuration.

The right way: pair work on critical areas, decisions in an ADR (architecture decision record), rotation across modules. Example calculation: one developer understands the bank integration — the bus factor is 1, and that is an entry in the risk register.

texta knowledge table in an md file
# bus_factor.md — who knows what in the team| Area              | People | Action                    ||-------------------|--------|---------------------------|| payment core      | 1      | pair work with a second   || mobile client     | 3      | rotation not needed       |

Further reading

Standards and bodies of knowledge — ISO 21502:2020, the PMBOK Guide, PRINCE2 — see the section “Standards and bodies of knowledge”. The economics of commitments and estimates — in the section “Project economics”.

Section sources

the section is written from these pages

Standards and bodies of knowledge

ISO 21500:2021 defines the concepts of a project, a programme and a portfolio, and ISO 21502:2020 is the guidance on project management. ISO/IEC/IEEE 12207:2026 covers software life cycle processes, ISO/IEC/IEEE 29148:2018 covers requirements engineering, and in CIS countries the technical specification is governed by GOST 34.602-2020.

Project management is not limited to ISO standards: the PMBOK Guide and BABOK Guide bodies of knowledge and the PRINCE2, Scrum and Kanban methodologies answer the same question in their own terms. Standards codify concepts and processes; bodies of knowledge codify practice.

Documents in force

DocumentWhat it definesStatusReplaced or supplemented by
ISO 21500:2021concepts of project, programme and portfolio managementedition 2, revision under way—
ISO 21502:2020guidance on project managementedition 1, revision under way—
ISO/IEC/IEEE 12207:2026software life cycle processesedition 2, April 2026replaced 12207:2017
ISO/IEC/IEEE 29148:2018requirements engineering, the SRS specificationconfirmed in 2024a new edition is in preparation
ISO/IEC 20000-1:2018requirements for a service management system (ITSM)confirmed in 2023amendment Amd 1:2024 on climate change
GOST 34.602-2020technical specification for automated system developmentin force since 1 January 2022replaced GOST 34.602-89
GOST 34.201-2020types and sets of documents for automated systemsin force since 1 January 2022replaced GOST 34.201-89
GOST R 59793-2021 and GOST R 59795-2021stages of automated system development and document contentin force since 30 April 2022—

Interstate standards of the GOST 34 complex are adopted by the Interstate Council for Standardisation (MGS); they are introduced in Uzbekistan through the Uzstandart index. GOST R 59792–59795-2021 are national standards of Russia: in Uzbekistan they are applied under a contract, not by default.

Stage 90.92 means the document is under revision; until it is complete, the document remains in force.

Bodies of knowledge and methodologies

  • PMBOK Guide — the eighth edition, November 2025: six principles and seven performance domains, from PMI.
  • PRINCE2 Project Management — a project management method; PeopleCert has owned the exams and standards since 2021, and the current version is Version 7.
  • Scrum Guide — the 2020 edition, the definition of Scrum by Ken Schwaber and Jeff Sutherland.
  • Kanban Guide — the May 2025 edition (v2025.5), a minimal description of the Kanban system.
  • BABOK Guide v3 — a body of knowledge for business analysis, six knowledge areas, from IIBA.
  • ITIL — a library for managing digital products and services; the owner is PeopleCert.
  • ISO/IEC 20000-1:2018 — the only certifiable standard in the list: organisations are audited against it for their service management system (ITSM).

What has changed in the latest editions

  • ISO/IEC/IEEE 12207:2026 — the second edition of the standard, published in April 2026, which withdrew the 2017 edition.
  • PMBOK Guide, eighth edition: brings back process guidance in a non-prescriptive form and expands the sections on AI, PMOs and procurement.
  • Kanban Guide 2025.5 replaces the 2020 edition; the work is licensed under CC BY-SA.
  • ITIL Version 5 (2026) renames “ITIL 4” to “ITIL” and puts the management of digital products and services at its centre; ITIL 4 certification continues in parallel.
  • ISO 21500:2021 and ISO 21502:2020 are under revision — stage 90.92 of the ISO five-year cycle.

Outdated documents still cited

  • GOST 34.602-89 — the old technical specification; it was replaced by GOST 34.602-2020, in force since 1 January 2022.
  • ISO/IEC/IEEE 12207:2017 — withdrawn when 12207:2026 came out, but still found in older contracts and internal regulations.
  • The sixth edition of the PMBOK Guide — the last one with process groups in their classic form; books about it are still in circulation.
  • Scrum Guide 2017 — the previous edition, before 2020: no Product Goal, with the development team nested inside the team.
  • ITIL 4 — the predecessor of Version 5; the name still appears in documents about processes.

Section sources

the section is written from these pages

End of the reference

What changed

revision history · 3 entries

Every edit is saved as a revision: a snapshot of the reference, the reason and a summary of changes. The published version changes only after the same checks as at creation.

  1. Manual edit

    reason: manual edit
  2. Manual edit

    reason: manual edit
  3. Reference updated

Weekly check

How the reference is checked

Once a week — and right after news of a release or a vulnerability — the reference is checked in three steps.

  1. 1. Freshness

    Sections are compared with the release notes and changelogs from the official sources and with the topic’s news.

  2. 2. Errors

    Every section is read again: wrong facts, outdated APIs and flags, broken examples.

  3. 3. Links — by an HTTP request

    Every source link must respond. A broken link is a reason to recheck the section.

No findings — only the date changes. Findings — only the affected sections are rewritten, and they appear in “What changed”. A new version replaces the published one only after passing the same checks as at creation.

Statuses

Verified
no findings
Updated
sections rewritten, edits are listed
Rechecking
while the check runs, the previous version stays open
Needs review
disputed points: the verified version is shown, editors review

Last check

10 Nov · Check · updated · no findings