The CAB reviews changes to the IT environment before they are implemented: it assesses the risks, the impact on services and how well the plans fit in with the work of other teams. The board meets on a regular basis and acts as a filter between the flow of requests and production infrastructure.
Who sits on the board and how the meeting runs
- change manager — chairs the meeting and owns the change calendar
- operations and support representatives — assess the impact on live services
- development or vendor representatives — explain the nature of the change and its consequences
- business or customer representatives — confirm the need and the priority
The board receives change requests: a description, a rationale, a risk assessment and a rollback plan. Decisions are recorded in the minutes: approved, rejected or deferred. Approved changes go into the change calendar, which shows when they will be carried out and by whom.
What the CAB assesses
| Criterion | Question |
|---|---|
| Impact | which services and users the change will affect, and what breaks if it fails |
| Risk | how likely a failure is and whether there is a tested rollback plan |
| Resources | the people needed, the maintenance window and the cost |
| Priority | how urgent the change is and whether it can be postponed |
| Interdependencies | whether the change conflicts with other work in the same window |
What bypasses the CAB
Not every change waits for the board. Standard changes — pre-approved, low-risk and well understood (for example, adding RAM under a standard procedure) — are carried out by following the procedure, without a meeting. Emergency changes to deal with major incidents are reviewed at short notice under an expedited procedure. This approach is described in ITIL.