CR — change request

A proposal to change the agreed scope, schedule, budget or configuration: it is drawn up as a document and goes through formal assessment and approval.

Also: request for change, RFC

checked 9 Nov

All terms

Requirements change even in a well-planned project: the client refines the tasks, the team uncovers hidden work, the market shifts priorities. A change request makes such a turn manageable: the impact on scope, schedule and budget is assessed first, then the change is approved — and only then is the plan changed.

What goes into a request

Part of the requestWhat it records
Changewhat is added, removed or reworked, and why it is needed
Estimatewhat it will cost: hours of work, money, a slip in the schedule; the new scope once approved
Impacthow the change affects schedule, budget, quality, risks and related work
Decisionapproval, rejection or deferral; who decided and on what grounds

How approval works

  1. The author describes the change and submits the request — it is registered and given a status.
  2. The team or an analyst assesses the impact: hours, budget, risks, dependencies on other work; a large change is also verified with tests.
  3. A designated body decides the fate of the request: in a project this is the sponsor or a change control board, in IT services — a designated approval authority, for example a change advisory board.
  4. An approved change is implemented and closed with a report on whether the estimate was met; a rejected one is recorded with its reasoning so that it is not quietly revived later.

Example

Midway through the project, the client asks to add two-factor authentication. The team estimates: 60 hours of work, a two-week slip in the release, a 5% budget increase. These figures go into the request, and the sponsor approves it on condition that two optional features move to the next version. Without the request the work would have been slipped in — and the schedule or quality would have suffered without the parties knowing.

Where a formal request is mandatory

Fixed-price contract projects and regulated industries run on change requests: without a documented change the work will not be paid for or accepted. In IT service management a request is the entry point for a change to a configuration: under ITIL, changes are divided into standard (recurring, pre-approved — no separate review needed), normal (they go through risk assessment and approval in the usual way) and emergency (urgent fixes via a fast track). The discipline here is not a formality: Google SRE experience suggests that roughly 70% of outages in production systems come from changes made to them.

In Scrum a scope change goes through the product backlog — the product owner changes the priority, and a separate document is not needed unless external commitments such as a contract or a service level agreement are affected.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • change management

    Change management is the process and its practices; a change request is a specific document within that process.

  • scope creep

    Scope creep is change accepted without assessment or documentation; the change request exists precisely to prevent that.

  • CABChange Advisory Board

    A CAB is the board that reviews change requests in IT services, not the document itself.

In depth in the references

where the topic is covered in detail