RTO — recovery time objective

A disaster recovery objective: the maximum time in which a service must be working again after a disaster — set by the business before an outage happens.

Also: service recovery time, allowable downtime

checked 9 Nov

All terms

RTO answers the question “how long can the service remain unavailable after a disaster”, while RPO answers “how much data may be lost in the process”. Both objectives are set by the business based on the impact of downtime on operations, not by the infrastructure team: they determine which disaster recovery and redundancy strategy to build and how much it will cost.

How RTO is set

The starting point is a business impact analysis (BIA): how much an hour of downtime costs and which processes must never be interrupted. A payment service needs an RTO measured in minutes, while an internal directory can live with a day of unavailability.

ServiceRTORPOWhat it takes
Payment processing15 minutes≈ 0Active copy in a second region
Online store1 hour5 minutesWarm standby: data replication, a scaled-down copy of the service
Internal directory24 hours24 hoursNightly copies in another region

The shorter the RTO, the more expensive the solution. NIST puts it plainly: the shorter the RTO, the more recovery solutions cost — zero downtime and a secondary site are far more expensive than a long RTO for a low-value system.

How RTO is achieved

AWS describes four disaster recovery strategies, from backups to an active deployment across two regions; each successive one shortens RTO and RPO but raises costs:

  • Backup and restore — infrastructure is redeployed from backups and IaC code: RTO in hours.
  • Pilot light — data is replicated and the core infrastructure is provisioned but powered off: RTO in tens of minutes.
  • Warm standby — a scaled-down but running copy of the service: RTO in minutes.
  • Active deployment in two regions — traffic goes to both: RTO is close to zero.

The objective is tested through drills: a backup is restored in a separate environment and the recovery is measured against the RTO. An untested plan is a hypothesis, not an objective.

RTO, RPO and MTD

NIST SP 800-34 defines RTO as the maximum time during which system components may remain unavailable without unacceptable impact on other resources and processes of the organisation, and ties it to MTD, the maximum tolerable downtime: RTO must be shorter than MTD, otherwise recovery itself would disrupt the business process. RPO is not part of MTD: it is a point in the past up to which data can be restored from the latest backup. After a disaster, the actual recovery time is compared with the objective: the figure from the plan is checked in practice rather than left on paper.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • RPOrecovery point objective

    RTO is the limit on downtime, while RPO is the limit on data loss: the point in the past up to which records will be restored.

  • MTTRmean time to recovery

    RTO is an objective from the DR plan, while MTTR is the actual average recovery time across real incidents.

  • HAhigh availability

    HA keeps the service running through routine failures, while RTO in the DR plan is the target for a disaster, when a site or region is lost.