PUE — PUE

Power Usage Effectiveness

A data centre energy efficiency metric: how much energy the facility spends in total for every kilowatt-hour that reaches the IT equipment.

Also: power usage effectiveness, data centre energy efficiency metric

checked 9 Nov

All terms

PUE shows how much of a data centre’s electricity reaches the servers, storage systems and network hardware, and how much is eaten by the support infrastructure: cooling, power supplies, losses in cabling and UPS units. The ideal is 1.0; the closer the value is to one, the less the facility wastes.

How it is calculated

text
PUE = total facility energy over a period / IT equipment energy over the same period
What countsExamples
IT equipmentservers, storage systems, network switches, KVM — the load the data centre exists for
Facility systemschillers, fans, pumps, CRAC units, dry coolers
Power and miscellanyUPS and transformer losses, PDUs, lighting, sensors, office space

PUE is measured by sensors at the facility input and on the lines feeding the IT load, usually over a year: in summer the cooling runs at a different load than in winter, and one-off readings are easy to mislead by. An underloaded data centre has a worse PUE: the facility systems run at full capacity while the IT load is small.

What the values look like

PUEWhat it means
1.0the theoretical ideal: all energy goes to the IT equipment, no losses or cooling
1.1–1.3the best modern facilities, most often hyperscale data centres with dense racks
about 1.5close to the average reported by Uptime Institute surveys
1.8–2.0 and abovelegacy server rooms without proper cooling

What PUE does not show

  • the efficiency of the IT machines themselves: a server may burn energy while idle, and PUE only gets better because of it
  • water consumption and the carbon footprint — there are separate metrics for these, WUE and CUE from the same The Green Grid family
  • straightforward comparability: data centres of different climate, scale and purpose can only be compared by PUE with caveats

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • Data centre Tier levels

    Tier reflects the fault tolerance of the facility infrastructure, not cost-effectiveness: redundancy adds components and can make PUE worse.

  • TDPthermal design power

    TDP is the rated heat dissipation of an individual processor, a chip characteristic; PUE is calculated for the data centre as a whole and its IT load.

In depth in the references