Story points are the team’s shared language for talking about task size. They let the team compare pieces of work with one another without immediately converting them into hours and days, which is why they took hold in agile methods such as Scrum and Extreme Programming. The numbers themselves don’t matter; what matters is their ratio: a 1–2–3 scale and a 10–20–30 scale describe the same difference.
What the estimate accounts for
| Factor | Example |
|---|---|
| Amount of work | a page with one field and a page with 100 fields differ in size, even though the fields themselves are identical |
| Complexity | 100 fields with no logic are simpler than 100 fields with date and card-number validation |
| Risk and uncertainty | a change in old code without automated tests is riskier than the same change in fresh code |
| Definition of done | points cover everything up to “done”: tests, review, documentation |
Taken together, points measure effort: size, complexity and risk combined. They don’t replace hours, and converting them into hours at a rate of “one point equals eight hours” is not worth doing: people work at different speeds, and the comparison falls apart straight away.
Planning poker
Points are usually assigned by the whole team together, most often in planning poker. Each player secretly picks a card with a number — a typical deck is 0, 1, 2, 3, 5, 8, 13, 20, 40, 100 — and everyone reveals their cards at the same time. If the estimates are close, the number is written down; if they diverge, the team discusses why: someone has factored in a risk the others didn’t think of. The secret choice and the simultaneous reveal keep players from anchoring on someone else’s estimate.
- The Fibonacci scale (1, 2, 3, 5, 8, 13…): each number is roughly one and a half times the one before, so the larger the estimate, the rougher it is. Large values are made even rougher: instead of 21 the deck uses 20 and adds 40 and 100.
- Reserved cards: “?” means “I don’t understand, it’s too early to estimate”, “☕” means “I need a break”.
- Large tasks are broken down into smaller stories: 40 or 100 on the scale usually means the task is too big to estimate reliably.
James Grenning proposed the poker method in 2002; it became widely known after Mike Cohn’s 2005 book “Agile Estimating and Planning”.
Why the team needs them
From the points taken into a sprint the team calculates its velocity — how many points it consistently completes per sprint — and uses that to forecast what will be ready by the release. The forecast rests on the team’s own track record: one team’s points cannot be compared with another’s.
Sources
the term is written from these pages- Mountain Goat Software — What Are Agile Story Points?mountaingoatsoftware.com/agile/what-are-story-points(opens in a new tab)
- Mountain Goat Software — Planning Pokermountaingoatsoftware.com/agile/story-points/planning-poker(opens in a new tab)
- Agile Alliance — Points (estimates in)agilealliance.org/glossary/points-estimates-in/(opens in a new tab)
Verified 9 Nov