Sprint

A fixed-length period of work, up to one month, in which the team builds and shows an increment of the product; the core working cycle in Scrum.

Also: iteration

checked 9 Nov

All terms

The sprint is the heartbeat of Scrum: a fixed period of one month or less, within which the team plans the work, builds an increment of the product and checks the result. A new sprint begins immediately after the previous one, so the flow of work is predictable: every few weeks it is clear what is done.

How a sprint works

All Scrum events take place within a sprint. For a month-long sprint, the Scrum Guide sets maximum time limits; shorter sprints usually have shorter events.

EventWhat happensTime limit for a month-long sprint
Sprint Planningtasks are picked from the backlog and the sprint goal is formulatedup to 8 hours
Daily Scrumin 15 minutes, the developers review their plan for the day15 minutes
Sprint Reviewthe team shows the result to the stakeholdersup to 4 hours
Sprint Retrospectivethe team discusses how to raise the quality and effectiveness of its workup to 3 hours

During a sprint, nothing is changed that would endanger the sprint goal — but the set of tasks can be clarified and re-agreed with the product owner as the team learns new things.

The sprint goal

Each sprint has a single goal — the Sprint Goal: a short statement of why the sprint is valuable. The goal is fixed at Sprint Planning and is not changed until the end of the sprint, while the team can reconsider which tasks to do for it and how. If the goal becomes obsolete — for example, the customer has closed the line of business — only the product owner may cancel the sprint.

Example of a two-week sprint

A team of six works in two-week sprints. Day one is a two-hour Sprint Planning session: the goal “move the shopping cart to the new payment API” and a list of tasks from the backlog. Every day at 11:00 there is a fifteen-minute Daily Scrum. On day ten comes the Sprint Review: the customer sees a working cart with the new payment method. On the last day there is a Sprint Retrospective, at which the team agrees not to keep more than two tasks per person in progress. From the story points it completed in past sprints (its velocity), the team estimates how many tasks to take on next.

Scrum, the framework in which the sprint is the central concept, was first presented by Ken Schwaber and Jeff Sutherland at the OOPSLA conference in 1995.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • kanban

    Kanban is a continuous flow of tasks with no fixed periods; a sprint sets a steady rhythm with a start and an end date.

  • team velocity

    Velocity is a metric: how many story points the team usually completes per sprint, while the sprint itself is a period of time.