Team velocity is measured from the results of past sprints and used for planning: how many items to take into the next sprint and roughly when the backlog will be ready. It is observation of the team, not a report to management: there are no benchmarks for “how fast a team should be”.
How it is calculated
Add up the story points of the stories the team fully completed during the sprint: a partly finished story does not count at all — completion is recognised as either 0% or 100%. The figure is then averaged over the last few sprints so that random spikes do not distort the picture.
| Sprint | Completed, points | Comment |
|---|---|---|
| 18th | 30 | a regular sprint |
| 19th | 34 | two people were on holiday, but the items happened to be small |
| 20th | 26 | half the sprint went on fixing an urgent bug |
| Average | 30 | used as the plan for the 21st sprint |
What it is for
- forecast: a 300-point backlog at a velocity of 30 points per sprint is about 10 sprints; the estimate is usually sound, but rarely accurate to the day;
- planning: the next sprint is filled with items worth roughly the average velocity, not “as much as fits”;
- warning light: if an item was not seen through to the end, or velocity swings sharply between sprints, this is a sign that the stories are too large and should be split.
Why it is not a KPI
Velocity is a measurement of what actually happened, not a budget and not a plan: saying “we will set a velocity for the team” betrays a misunderstanding of the metric. Only the velocity of the whole team counts — “individual velocity” is meaningless. Teams cannot be compared with each other either: each has its own story point scale, so 30 points for one team and 60 for another say nothing about their productivity. It is also wrong to set a goal of “raising velocity”: the team then inflates estimates and splits items, while actual throughput does not change. Fluctuations between sprints due to leave, public holidays and urgent bugs are normal.
The Scrum Guide does not mention velocity — the guide defines events and artefacts, not metrics. The term grew out of extreme programming: in 2000 it appeared in XP replacing “load factor”, and from 2002 velocity measurement was picked up by the scrum community.