WIP stands for work in progress: items the team has taken on but not yet finished. An explicit WIP limit is one of the core kanban practices: without it the board only shows the process but does not control it. The motto of the practice is “stop starting, start finishing”.
How the limit works
On a kanban board the limit is set on a column: for example, “Review — no more than 2”. While the column has free space, the next item is pulled from the queue into work; when there is no space, no new item is taken on, even if people are free — first the team finishes or passes on what has already been started. This is how a pull system works: the next piece of work starts only once capacity has become available.
| Column | Limit | Why |
|---|---|---|
| In progress | 3 | one item per developer, no parallel unfinished work |
| Review | 2 | if review falls behind, items pile up in front of the column and the bottleneck is visible straight away |
| Done | — | finished items are pulled as the next stage frees up |
The limit applies not only to a column but also to the whole process or to a single person. It makes the problem visible: a column with a queue in front of it is the bottleneck, and the team can get together and deal with it. Keeping people fully loaded harms the flow: when everyone is busy, items sit in queues like cars in a traffic jam.
Little’s law
The law is named after John Little, who proved it in 1961: the average number of items in a system equals the throughput multiplied by the average time an item spends in the system. Work in progress (WIP) is one of the key kanban metrics alongside lead time and throughput.
WIP = Throughput × Lead Time # 8 items in progress, the team finishes 4 items a day# 8 / 4 = 2 days — average time from start to finish# raise WIP to 16 at the same speed and the time grows to 4 daysThe practical takeaway: at the same team speed, the more work in progress, the longer each item takes. A WIP limit holds the number of items at a level where lead time stays short and predictable.
How the value is chosen
- start from the current number of items in the column — the limit is set slightly below what is there now
- a column with several people gets a limit lower than the number of people — this leaves the team slack to help each other and finish what has been started
- review the limit against data: a queue in front of the column means it is too high, idle people mean it is too low
- the limit is an explicit team agreement: under the kanban guide, everyone taking part in the process should agree on it