The name comes from the Toyota production system, where cards — kanban — authorise the production or transfer of a required number of parts to the next stage. In software development, kanban is a board with columns and limits: the team works in a continuous flow, with no sprints and no prescribed roles.
How a board is arranged
| Board element | What it does |
|---|---|
| Columns | stages of work: for example “To do”, “In progress”, “Review”, “Done” |
| Cards | units of work: tasks, defects, user requests |
| WIP limit | the maximum number of cards in a column: no more than 3 in “In progress” |
| Flow policies | the team’s agreement on how an item passes through the stages of the flow from start to finish |
The board makes the system pull-based: a new item is taken on only when the column’s limit allows it. The limit is not about speed but about focus: the less is started, the faster the started work gets finished.
Three practices and four metrics
The Kanban Guide describes the system through three practices: define and visualise the workflow, actively manage the items in the flow and improve it continually. Four mandatory metrics describe the flow:
| Metric | What it measures |
|---|---|
| WIP | the number of items started but not finished |
| Throughput | the number of items finished per unit of time |
| Item age | the time from when work on an item started to the current day |
| Cycle time | the time from when work on an item starts to when it ends |
From the metrics follows the service level expectation — a forecast such as “85% of items will be finished in 8 days or sooner”; until there is historical data, it is taken as an informed assumption. Average cycle time is tied to Little’s law: the average number of items in progress equals the average cycle time multiplied by the throughput.
Kanban and Scrum
Kanban is not tied to an industry or a scale, and has no prescribed roles, events or sprints — changes are taken into the flow at any moment. For software development, a set of kanban practices was assembled in 2006 at Corbis, after which it spread through the international community. It suits best where work arrives unpredictably: support, operations, request intake. The approaches do not compete: teams work in sprints and at the same time keep a board with WIP limits.