A Gantt chart is the familiar picture of a project plan: a list of work on the left, a time scale across the top, and each job as a bar from start to finish. It shows what is going on now, what starts after what, and where the project risks missing its deadline.
What you see on the chart
| Element | What it shows |
|---|---|
| Bar | a single task: when it starts and ends, how long it lasts |
| Time scale | the planning units — days to months, at the top or the bottom |
| Dependency arrow | a link between tasks: the next one cannot start until the previous one is finished |
| Milestone | a checkpoint with no duration — a release, acceptance, signing off a contract; drawn as a diamond |
| Bar fill | the share of work completed — the percentage done as of the current date |
| Resource row | who does the task: an assignee or a team |
Where the term comes from
The chart was devised and popularised around 1910–1915 by the American engineer Henry Gantt, and his name stuck in the title. Early charts were drawn by hand and redrawn with every change to the plan; today the chart is built into most project management tools, from Microsoft Project to Jira and OpenProject.
When it helps and when it gets in the way
The chart works well where the plan is known in advance and the dates are fixed: construction, an infrastructure migration, a project with contractual deadlines. For such a project it also serves as a report for management: one picture instead of a long table.
Trouble starts when the plan changes daily: bars have to be moved by hand, and the chart goes stale faster than it is updated. That is why in iterative development the plan for the sprint lives on a task board, and a Gantt chart is drawn for projects with a strong schedule or at the top level of the plan.