WBS — work breakdown structure

A project planning tool: the hierarchical breakdown of all the work needed to deliver a result into manageable parts, each with its own deliverable and estimate.

Also: work decomposition, WBS

checked 9 Nov

All terms

A WBS answers the question of which pieces of work add up to a project’s deliverable. The schedule and budget estimates, the timeline and the assignment of responsibility all grow out of it, which is why the structure is built early in planning — before the Gantt chart and the cost estimate. A WBS dictionary usually accompanies the structure: a description of each element that rules out double interpretation and overlap.

How the hierarchy is built

The structure is built top-down: first the project’s final deliverable is fixed, then it is progressively divided into smaller and more manageable parts. The lowest level consists of work packages: they can be estimated in effort, assigned an owner and checked against completion criteria.

LevelWhat it containsExample for the project “E-commerce website”
1the whole project, its final deliverable“A launched online store”
2the major products of the project“Store”, “Admin panel”, “Launch and promotion”
3 and belowthe components of a product“Catalogue”, “Cart”, “Payments”
Work packagea terminal part that is not divided further“Payment gateway integration”: estimate, deadline and a single owner

The division follows deliverables, not departments, functions or dates. Phases such as “Design” or “Production”, job titles and project phases are not products: design is a function rather than a part of the result, and the NASA handbook names such elements as a typical WBS construction mistake. The depth is not arbitrary either: a level is considered sufficient when an element can be planned, estimated and assigned.

The 100% rule

A WBS includes exactly 100% of the work needed for the project’s deliverable — and nothing beyond it. Any less and the plan will miss something important; any more and the structure will take in work that has nothing to do with the result. Whatever is not in the structure does not count towards the project scope: “work not in the WBS is not part of the project” is how the NASA handbook puts it.

  • each element has a single parent: an amplifier is not a branch “inside the transmitter” but a sibling element of the same subsystem;
  • the sum of the lower-level work at every node equals the scope of that node — nothing is lost and nothing is added;
  • once the baseline is fixed, the structure changes only through a formal change procedure — with justification and approval from the project manager

This is how a WBS serves as the first line of defence against scope creep: new work is either built into the structure through a change request or does not enter the project scope at all.

What a WBS does not include

The structure describes the scope of work only. The other planning attributes are not included in it:

  • durations, dates and dependencies between tasks — that is the schedule, built on top of a finished WBS;
  • owners — they are assigned to elements, usually with a RACI matrix;
  • cost — it is estimated for the elements of the structure and aggregated up the levels

This is why a WBS is often confused with a project plan or a Gantt chart, although the order is the other way round: first the decomposition, then the calendar and the budget. The approach grew out of United States defence programmes: for military procurement the composition of a WBS is set by the MIL-STD-881 standard, and PMI consolidated the practice in a separate Practice Standard for Work Breakdown Structures.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • Gantt chart

    On a Gantt chart the tasks from the WBS acquire durations and dependencies and turn into a schedule; the WBS itself carries no dates.

  • roadmap

    A roadmap shows major milestones over months and years, while a WBS is the full decomposition of the work of a single project with no dates attached.