A WBS answers the question of which pieces of work add up to a project’s deliverable. The schedule and budget estimates, the timeline and the assignment of responsibility all grow out of it, which is why the structure is built early in planning — before the Gantt chart and the cost estimate. A WBS dictionary usually accompanies the structure: a description of each element that rules out double interpretation and overlap.
How the hierarchy is built
The structure is built top-down: first the project’s final deliverable is fixed, then it is progressively divided into smaller and more manageable parts. The lowest level consists of work packages: they can be estimated in effort, assigned an owner and checked against completion criteria.
| Level | What it contains | Example for the project “E-commerce website” |
|---|---|---|
| 1 | the whole project, its final deliverable | “A launched online store” |
| 2 | the major products of the project | “Store”, “Admin panel”, “Launch and promotion” |
| 3 and below | the components of a product | “Catalogue”, “Cart”, “Payments” |
| Work package | a terminal part that is not divided further | “Payment gateway integration”: estimate, deadline and a single owner |
The division follows deliverables, not departments, functions or dates. Phases such as “Design” or “Production”, job titles and project phases are not products: design is a function rather than a part of the result, and the NASA handbook names such elements as a typical WBS construction mistake. The depth is not arbitrary either: a level is considered sufficient when an element can be planned, estimated and assigned.
The 100% rule
A WBS includes exactly 100% of the work needed for the project’s deliverable — and nothing beyond it. Any less and the plan will miss something important; any more and the structure will take in work that has nothing to do with the result. Whatever is not in the structure does not count towards the project scope: “work not in the WBS is not part of the project” is how the NASA handbook puts it.
- each element has a single parent: an amplifier is not a branch “inside the transmitter” but a sibling element of the same subsystem;
- the sum of the lower-level work at every node equals the scope of that node — nothing is lost and nothing is added;
- once the baseline is fixed, the structure changes only through a formal change procedure — with justification and approval from the project manager
This is how a WBS serves as the first line of defence against scope creep: new work is either built into the structure through a change request or does not enter the project scope at all.
What a WBS does not include
The structure describes the scope of work only. The other planning attributes are not included in it:
- durations, dates and dependencies between tasks — that is the schedule, built on top of a finished WBS;
- owners — they are assigned to elements, usually with a RACI matrix;
- cost — it is estimated for the elements of the structure and aggregated up the levels
This is why a WBS is often confused with a project plan or a Gantt chart, although the order is the other way round: first the decomposition, then the calendar and the budget. The approach grew out of United States defence programmes: for military procurement the composition of a WBS is set by the MIL-STD-881 standard, and PMI consolidated the practice in a separate Practice Standard for Work Breakdown Structures.