Besides the team, a project always has people with a stake in its outcome: a sponsor, users, an operations team, a regulator. Their interests differ and collide, so stakeholders are identified in advance, mapped by influence and interest, and communicated with according to a plan — otherwise requirements arrive midway through the work and acceptance falls apart.
Who counts as a stakeholder
| Stakeholder | Their interest | Example in an IT project |
|---|---|---|
| Sponsor | return on investment, deadlines | a director who allocated budget for replacing the CRM |
| Customer | a business problem solved | the head of sales the CRM is built for |
| Users | ease and speed of their work | operators who spend the whole day in that CRM |
| Team and contractors | clear requirements, payment | a systems integrator, a contractor hired for data migration |
| Related departments | reliability and support | operations, accounting, information security |
| Regulators and society | legality, data protection | a personal data supervisory authority |
Influence and interest matrix
To decide who to engage closely and who it is enough to keep informed, stakeholders are plotted on two axes: influence and interest. This matrix is known as the Mendelow matrix; the Mitchell, Agle and Wood classification sorts stakeholders by power, the legitimacy of their claims and urgency (1997).
| Influence | Interest | What to do |
|---|---|---|
| high | high | manage closely: involve them in decisions and agree on the key steps |
| high | low | keep them in the loop and warn of risks early so they do not disrupt unexpectedly |
| low | high | keep informed regularly: demos, progress reports |
| low | low | monitor, giving them minimal attention |
How the standards handle them
The project management guidance ISO 21502:2020 describes work with stakeholders; in the 6th edition of the PMBOK Guide a whole knowledge area is devoted to it, and in the 7th, a performance domain. The tools are the same: a stakeholder register capturing interests, expectations and degree of influence, an engagement plan and a communications plan. The register is updated as the project progresses: a stakeholder who resisted the change yesterday may champion it tomorrow.
In Scrum, the team shows the sprint result to key stakeholders at the Sprint Review and together with them decides what to do next. The term “stakeholder” was first used in 1963 in a Stanford Research Institute memorandum, and the idea was developed by R. Edward Freeman in the book “Strategic Management: A Stakeholder Approach” (1984).
Sources
the term is written from these pages- NIST SP 800-160 Vol. 1 Rev. 1 — Systems Security Engineering (глоссарий CSRC, статья stakeholder)csrc.nist.gov/glossary/term/stakeholder(opens in a new tab)
- ISO 21502:2020 — Guidance on project management (страница стандарта)iso.org/standard/74947.html(opens in a new tab)
- The Scrum Guidescrumguides.org/scrum-guide.html(opens in a new tab)
Verified 9 Nov