RACI settles in advance a typical question of project work — “who is in charge of this task”. For each task or decision, the rows of the matrix list the team’s roles and assign each of them one of four letters. This removes two extremes at once: “everyone is responsible for everything” and “the task has been dumped on a person with no authority to do it”.
The four roles
| Letter | Role | What it means |
|---|---|---|
| R — Responsible | The doer | performs the work; there can be several performers |
| A — Accountable | The owner | owns the result: signs off and approves the work; by the rules — exactly one per task |
| C — Consulted | Those consulted | give an opinion before a decision or action; two-way communication |
| I — Informed | Those informed | are given updates on progress and results; one-way communication |
How to make one
- list the tasks or decisions line by line — from large stages down to individual pieces of work;
- in the columns — roles, job titles or specific people;
- in a cell — one letter or nothing; if a person both does the work and is accountable for it, both letters are written — R-A;
- check that every row has exactly one A and at least one R;
- show the matrix to the team and agree on the disputed cells before the work starts.
Example
The task — migrating a database to a new PostgreSQL cluster:
| Task | Developer | Team lead | DBA | Product manager | Operations team |
|---|---|---|---|---|---|
| Migration plan | R | A | C | I | C |
| Downtime window | C | C | R | A | C |
| Customer notification | I | I | I | A | R |
Where it is used and what comes next
RACI is used in project plans, process guidelines and at the start of work, to settle areas of responsibility before conflicts arise — including when several teams or departments work on the same result. If the four roles are not enough, extended variants are used: RASCI adds the role S — Support, helpers of the doer, while in DACI the doer gives way to the Driver — the person who drives the work.
Sources
the term is written from these pages- Atlassian — RACI chart templateatlassian.com/software/confluence/templates/raci-chart(opens in a new tab)
- Microsoft Learn — Microsoft Managed Desktop RACI matrixlearn.microsoft.com/en-us/previous-versions/managed-desktop/references/raci(opens in a new tab)
- Atlassian — DACI: Decision documentation templateatlassian.com/software/confluence/templates/decision(opens in a new tab)
Verified 9 Nov