Fixed Price and Time & Materials contracts

fixed price, time and materials

The two basic payment models for IT projects: Fixed Price — a fixed sum for an agreed scope of work; Time & Materials — payment for the time and resources actually spent.

Also: fixed-price contract, time-and-materials contract, T&M, fixed price

checked 9 Nov

All terms

Almost any development engagement is paid for under one of these schemes, and the choice between them is above all an answer to the question of who pays for uncertainty: the contractor, who builds the risks into a fixed price, or the customer, whose budget stays open until the work is done.

Who carries the risk

RiskFixed PriceTime & Materials
Error in the effort estimatecarried by the contractor: the contract sum does not changecarried by the customer: pays for every hour actually spent
Change in scopeonly through a change request with a revised pricereprioritisation is part of the ongoing payment
Final budgetknown before the work startsopen; sometimes capped by a spending ceiling
Requirements at the startcomplete and stable requirements, a detailed technical specificationa goal and a general understanding are enough; details are clarified along the way
Contractor’s incentiveto stay within the estimate, so the risks are built into the price in advanceto account for the hours honestly, so reporting and customer oversight are needed

When each model is chosen

  1. Fixed Price — when the scope is known and stable: typical implementations, migrations, work with a ready-made detailed technical specification.
  2. Time & Materials — when the scope is unclear in advance: product development, research and prototypes, support, reinforcing the team with specialists.
  3. Hybrids — a fixed price per sprint or phase, Time & Materials with a budget cap (not-to-exceed), a dedicated team paid by the month.

How the price adds up

Under Fixed Price the contractor estimates the work, adds a risk buffer and fixes the sum: if its estimate comes to 1,000 hours, or 1,200 with the buffer, the work will be sold at 1,200, and any overrun beyond the estimate is the contractor’s to absorb. Under Time & Materials the bill is made up of hours actually logged at agreed rates: at a rate of 100 units an hour, two specialists at 160 hours a month will cost the customer 32,000 units. Fixed Price payments are usually tied to milestone acceptance, while Time & Materials invoices go out monthly against timesheets. To keep the budget from melting away, a spending ceiling is written into almost every T&M contract — the customer’s simplest insurance.

How they are enshrined in procurement practice

In FAR, the American body of rules for government procurement, the firm-fixed-price contract is the model with the greatest risk for the contractor: the price is not revised against its actual costs, and it is chosen where the requirements are described precisely enough for a price to be set in advance. Under FAR, Time & Materials is not a fixed-price model at all: payment is made for hours of labour at rates set in advance (they include wages, overheads and profit) plus the actual cost of materials, and the contract sets a ceiling price that the contractor exceeds at its own risk.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • SOWstatement of work

    The SOW describes the scope of work and the deliverables; a contract of any type needs one, while Fixed Price and Time & Materials define how that work is paid for.

  • outsourcing and outstaffing

    Outsourcing and outstaffing answer who does the work, while Fixed Price and Time & Materials answer how it is paid for.