SOW — statement of work

A document that records, in the contract, the scope of the contractor’s work: what they do, which deliverables they hand over, by when, and how those deliverables are accepted.

Also: statement of work, SOW

checked 9 Nov

All terms

The SOW is the working part of the contract between the customer and the contractor: without it, the parties agree on a price but not on what exactly that price is paid for. Usually the customer prepares the statement of work and includes it in the request for proposals; once the contractor has been selected, the document is refined and written into the contract. From then on, the SOW underpins the project plan, the budget and the acceptance procedure.

What an SOW contains

SectionWhat it fixes
Objectives and contextwhy the project is needed, which product or system it belongs to
Scope of workwhat the contractor does and what remains on the customer’s side; what falls outside the scope
Deliverablesconcrete deliverables: a document, a working service, code, training, rights to them
Schedule and stagesstart and delivery dates, milestones, dependencies on the customer
Acceptancewho accepts each deliverable and against which criteria, the time allowed for fixes
Paymentthe amount and the payment schedule, tied to the stages
Constraintssecurity requirements, work on the customer’s premises, confidentiality

Types of statement of work

  • Detailed — the work is specified in full: composition, steps, specifications; it suits cases where the customer knows the solution exactly.
  • Effort-based — the team’s work is paid at rates and by the hour, for tasks whose volume cannot be measured in advance.
  • Performance-based — the requirements for the result and the acceptance criteria are fixed, while how the work is done is left to the contractor.

The type determines the contract: a detailed or performance-based statement of work usually goes with a fixed-price contract, while an effort-based one goes with Time & Materials. General terms are often fixed in a master service agreement, and then the SOW for each engagement describes only the specific scope. A detailed statement of work is conveniently broken down by a work breakdown structure (WBS): each of its elements becomes a subsection. In practice, a single document combines approaches: a fixed-price stage followed by support paid by the hour.

Example

A customer commissions the development of a corporate portal. The SOW has three stages of four months each: concept and design (a prototype, a design system), development (working services in a test environment), and launch (acceptance testing, documentation, training). Each stage ends with a deliverable that has a date and acceptance criteria; after acceptance, payment follows. New scope is handled through a change request; otherwise it is scope creep.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • ТЗtechnical specification

    The technical specification describes what the outcome should be and under which requirements; the SOW sets who does what, and by when, under the contract.

  • RFPrequest for proposal

    An RFP is a request through which the customer is still selecting a contractor; the statement of work is usually already enclosed in it and moves into the contract once the choice is made.

  • SLAservice level agreement

    An SLA sets the level of service for a service in operation, while the SOW sets the scope of work that leads to that outcome.

In depth in the references

where the topic is covered in detail