The SOW is the working part of the contract between the customer and the contractor: without it, the parties agree on a price but not on what exactly that price is paid for. Usually the customer prepares the statement of work and includes it in the request for proposals; once the contractor has been selected, the document is refined and written into the contract. From then on, the SOW underpins the project plan, the budget and the acceptance procedure.
What an SOW contains
| Section | What it fixes |
|---|---|
| Objectives and context | why the project is needed, which product or system it belongs to |
| Scope of work | what the contractor does and what remains on the customer’s side; what falls outside the scope |
| Deliverables | concrete deliverables: a document, a working service, code, training, rights to them |
| Schedule and stages | start and delivery dates, milestones, dependencies on the customer |
| Acceptance | who accepts each deliverable and against which criteria, the time allowed for fixes |
| Payment | the amount and the payment schedule, tied to the stages |
| Constraints | security requirements, work on the customer’s premises, confidentiality |
Types of statement of work
- Detailed — the work is specified in full: composition, steps, specifications; it suits cases where the customer knows the solution exactly.
- Effort-based — the team’s work is paid at rates and by the hour, for tasks whose volume cannot be measured in advance.
- Performance-based — the requirements for the result and the acceptance criteria are fixed, while how the work is done is left to the contractor.
The type determines the contract: a detailed or performance-based statement of work usually goes with a fixed-price contract, while an effort-based one goes with Time & Materials. General terms are often fixed in a master service agreement, and then the SOW for each engagement describes only the specific scope. A detailed statement of work is conveniently broken down by a work breakdown structure (WBS): each of its elements becomes a subsection. In practice, a single document combines approaches: a fixed-price stage followed by support paid by the hour.
Example
A customer commissions the development of a corporate portal. The SOW has three stages of four months each: concept and design (a prototype, a design system), development (working services in a test environment), and launch (acceptance testing, documentation, training). Each stage ends with a deliverable that has a date and acceptance criteria; after acceptance, payment follows. New scope is handled through a change request; otherwise it is scope creep.