An RFP is a formal step in procurement, taken once the buyer already knows what it needs and wants comparable proposals from the market: every participant gets the same requirements, the same deadlines and the same response format. An RFP response is usually treated as an offer — if the buyer accepts it, a contract comes into being, so the criteria are announced in advance.
What goes into an RFP
- introduction and context: who the buyer is, what the problem is, the goals and constraints;
- requirements: functional and non-functional, mandatory and desirable;
- weighted evaluation criteria: technical solution, team, track record, price, support;
- format and timing: response structure, submission deadline, selection stages, contacts for questions;
- contract terms: the type (fixed price or time and materials), timescales, warranties, acceptance.
How proposals are compared
The evaluation criteria and their relative weight are announced in advance — in the RFP documentation itself: only then are proposals comparable with one another and can the choice be explained. For example, the scale might be: technical solution 40%, track record and references 20%, team 20%, price 20%. Every participant is scored on the same scale; price is often assessed separately from the technical part — by comparing the bids.
Where the RFP sits in the procurement chain
The RFP sits between preliminary market research and a purchase of well-understood scope:
| Request | What it is for | Is the response binding |
|---|---|---|
| RFI — request for information | to learn the market: which solutions and suppliers exist at all | no: a response does not create a contract |
| RFP — request for proposal | to obtain solutions and prices against stated requirements and criteria | yes: a response is an offer, acceptance brings the contract into being |
| RFQ — request for quotation | to obtain a price for a scope that is already well understood | a quotation; the contract follows acceptance |
Example
A retailer is choosing a contractor to implement a WMS. The RFP covers integration with the ERP and tills, a 99.9% SLA at peak hours, acceptance against a scenario of 200 orders per hour, and a six-month timescale. Three weeks for questions and answers, then proposal submission, scoring against the announced scale, pilot implementations at one warehouse for the two finalists, and after them a fixed-price contract.