PRINCE2 methodology

A project management method that divides work into manageable stages and keeps the project under control through explicit roles, business justification and management by exception.

Also: Projects IN Controlled Environments

checked 9 Nov

All terms

PRINCE2 (Projects IN Controlled Environments) is a structured project management method: it describes how to organise work from start to closure — the roles, stages, documents and decision points. More than a million practitioners in 150+ countries have been certified in the method.

What the method consists of

The method rests on three groups of elements — principles, practices and processes, seven in each:

ElementNumberWhat it defines
Principles7the ground rules without which a project cannot be called a PRINCE2 project; cannot be tailored
Practices7what must be maintained continuously in the project: the business case, plans, risks, quality, issues and changes; called themes before the seventh edition
Processes7who does what and when — from preparing the project to closing it

The principles include continued business justification, learning from experience, defined roles and responsibilities, management by stages, a focus on products and tailoring the method to the project at hand. The practices and processes may be scaled: from a small project to a large programme.

Roles, stages and tolerances

The project is directed by a project board made up of business, user and supplier representatives. The board delegates tolerances to the project manager — limits on time, budget and other measures. While work stays within tolerance, the project manager acts on their own; a threat of exceeding the limits is an exception, which is escalated to the board. This arrangement is called management by exception and protects senior management’s time.

  • The business case — the justification for the project; it is updated at every stage, and the project is closed if the benefit disappears.
  • PID (project initiation document) — the starting document: the approach, roles, plan and the management of quality, risks and changes.
  • Stage plans and work packages — breaking the work down into measurable deliverables.
  • Risk and issue registers and stage reports — the basis for the board’s decisions between stages.

History, versions and certification

The method grew out of PRINCE, a 1989 standard for IT projects of the UK government; the second edition, PRINCE2, was released in 1996 as a general-purpose project management method. Rights to the method changed hands several times, and since 2021 it has been owned by PeopleCert. The current edition is PRINCE2 7, released in September 2023: it strengthened the handling of people, tailoring to the project, digital data and sustainability, and is claimed to be compatible with Agile, Lean and ITIL.

Certification has two levels: Foundation tests knowledge of the method, Practitioner the ability to apply and tailor it in one’s own project. Besides the core method, the PeopleCert portfolio includes PRINCE2 Agile and qualifications in programme, portfolio and risk management.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • PMBOKProject Management Body of Knowledge

    PMBOK is PMI’s body of knowledge on project management, without a single scheme for running a project; PRINCE2 is a method with roles, stages and mandatory documents.

  • Agile

    Agile sets values and flexible working cycles for a team; PRINCE2 describes project governance as a whole and, in its seventh edition, is compatible with agile practices.

  • ITILITIL library

    ITIL describes the management of IT services in operation, while PRINCE2 covers the management of projects; both practice libraries belong to PeopleCert.

In depth in the references

where the topic is covered in detail