PRINCE2 (Projects IN Controlled Environments) is a structured project management method: it describes how to organise work from start to closure — the roles, stages, documents and decision points. More than a million practitioners in 150+ countries have been certified in the method.
What the method consists of
The method rests on three groups of elements — principles, practices and processes, seven in each:
| Element | Number | What it defines |
|---|---|---|
| Principles | 7 | the ground rules without which a project cannot be called a PRINCE2 project; cannot be tailored |
| Practices | 7 | what must be maintained continuously in the project: the business case, plans, risks, quality, issues and changes; called themes before the seventh edition |
| Processes | 7 | who does what and when — from preparing the project to closing it |
The principles include continued business justification, learning from experience, defined roles and responsibilities, management by stages, a focus on products and tailoring the method to the project at hand. The practices and processes may be scaled: from a small project to a large programme.
Roles, stages and tolerances
The project is directed by a project board made up of business, user and supplier representatives. The board delegates tolerances to the project manager — limits on time, budget and other measures. While work stays within tolerance, the project manager acts on their own; a threat of exceeding the limits is an exception, which is escalated to the board. This arrangement is called management by exception and protects senior management’s time.
- The business case — the justification for the project; it is updated at every stage, and the project is closed if the benefit disappears.
- PID (project initiation document) — the starting document: the approach, roles, plan and the management of quality, risks and changes.
- Stage plans and work packages — breaking the work down into measurable deliverables.
- Risk and issue registers and stage reports — the basis for the board’s decisions between stages.
History, versions and certification
The method grew out of PRINCE, a 1989 standard for IT projects of the UK government; the second edition, PRINCE2, was released in 1996 as a general-purpose project management method. Rights to the method changed hands several times, and since 2021 it has been owned by PeopleCert. The current edition is PRINCE2 7, released in September 2023: it strengthened the handling of people, tailoring to the project, digital data and sustainability, and is claimed to be compatible with Agile, Lean and ITIL.
Certification has two levels: Foundation tests knowledge of the method, Practitioner the ability to apply and tailor it in one’s own project. Besides the core method, the PeopleCert portfolio includes PRINCE2 Agile and qualifications in programme, portfolio and risk management.