Risk register

A document that gathers the risks of a project or an organisation: the assessment of probability and impact, an owner and the chosen response for each risk.

Also: risk log, project risk register, risk register

checked 9 Nov

All terms

A risk register is a working list of the threats to a project or business and the plan for each of them. It is maintained throughout the work: new risks are found, existing ones are reassessed, completed responses are ticked off and out-of-date entries are closed. It is usually one table, not a separate document for each risk.

What is recorded

The team chooses the set of fields itself, but most often they match the list from OMB Circular A-11, which NIST quotes: the risk description, the impact if it happens, the probability, the mitigation measures, the owner and a rank for prioritisation.

FieldWhat is recorded
Descriptionwhat may happen and what the harm would be: “the server delivery will be a month late”
Probability and impacta rating in points or in words — low, medium, high
Ownerthe person who keeps an eye on the risk and is answerable for the response to it
Responsethe plan of action: eliminate, reduce, transfer or accept the risk
Rankthe place in the list by priority, so that the important things are dealt with first
Statusopen, in progress, closed

Response to a risk

For negative risks NISTIR 8286 describes four standard responses:

  • eliminate (avoid) — remove the cause of the risk: drop a risky technology or stage;
  • reduce (mitigate) — lower the probability or the impact: backups, a second supplier;
  • transfer (transfer) — hand part of the risk to a third party: insurance, a contract with penalties;
  • accept (accept) — leave it as it is and monitor, if the impact stays within the acceptable limit.

Positive risks — opportunities — are treated in the mirror way: exploit them, share them with a partner, enhance them or accept them. The priority is often calculated as probability multiplied by impact: 3 × 4 = 12 will be placed above 2 × 2 = 4.

Who keeps it and how

Each risk in the register has an appointed owner, and the whole team should add to it: at team meetings, when the scope of work changes and after incidents. In large organisations the registers of departments are consolidated into an enterprise-wide register, where the risks are normalised and ranked by priority — this is how the management sees the whole portfolio. There is no rigid standard for the form: the company’s methodology sets the format, and the register is kept in a spreadsheet, in Jira or in risk management systems.

Sources

the term is written from these pages

Verified 9 Nov

Not to be confused with

what it is mixed up with and how it differs

  • RAID log

    A RAID log brings risks, assumptions, issues and dependencies together in a single list; a risk register deals with risks only.

In depth in the references

where the topic is covered in detail