The log is a working tool for the project manager: it is reviewed at status meetings and kept alongside the plan so that small threats do not turn into missed deadlines.
What goes into the log
| Section | What it is | Example |
|---|---|---|
| Risks | things that may happen; each is assessed for probability and impact and given a response | a vendor will delay access to the API |
| Assumptions | things taken as true without verification; if an assumption proves wrong, the row becomes a risk or an issue | the client will provide test data by March |
| Issues | things that have already happened and are getting in the way of work; every issue has an owner and a resolution date | the test environment has been unavailable for the third week |
| Dependencies | who and what the project depends on: other teams, deliveries, licences | the mobile app is waiting for the backend release |
Other expansions are also found: actions instead of assumptions, decisions instead of dependencies; sometimes the letters are combined. Only the set of columns differs, the purpose of the log does not.
How the log is maintained
- each row has a description, an owner, a due date and a status — not an entire department as the “responsible party”;
- risks are sorted by probability and impact, with the ones that could derail the schedule or the budget at the top;
- the log is reviewed at the status meeting — usually weekly or once per sprint;
- a row is closed when the risk has not materialised or the issue is resolved, and a risk that has grown is moved to issues.
Example row: “the payment provider has not confirmed the certification date” — a risk, medium probability, high impact, owner: the integration lead, response: bring in a backup provider by 20 November.
Format and standards
A RAID log is kept in a table, a wiki or a task tracker — the format matters less than the discipline of updating it. Clients and auditors often ask to see it: the log shows at once what the project is busy with beyond an “all on track” status. The resemblance to the RAID disk array is purely one of letters — the term has nothing to do with data storage.
There is no separate standard for the log — it is a practice rather than part of a methodology: bodies of knowledge such as PMBOK describe individual artefacts — a risk register, an assumptions log, an issue log — and do not require combining them into one table.
Sources
the term is written from these pages- APM Glossary of Project Management Termsapm.org.uk/resources/glossary/(opens in a new tab)
- IPA (GOV.UK) — Gate 1 Review: Business Justification (RAID log)assets.publishing.service.gov.uk/media/60f0188dd3bf7f568e1f6463/1174-APS-1-CCS0521656666-001_IPA_Gateway_Web1.pdf(opens in a new tab)
- APM — Simple solution to the constraint complaintapm.org.uk/blog/simple-solution-to-the-constraint-complaint/(opens in a new tab)
Verified 9 Nov