An RFI is the first, exploratory step of a procurement. The customer is not yet choosing a supplier and does not require binding prices: it describes its task and asks the market to explain how the task can be solved at all. Answers to an RFI bind neither the customer nor the respondents.
Place in the procurement chain
RFI, RFP and RFQ answer different questions and come at different stages of procurement maturity.
| Request | Purpose | Is the answer binding |
|---|---|---|
| RFI — request for information | learn about the market: which solutions, products and approaches exist | no: an answer is not an offer and creates no contract |
| RFP — request for proposals | obtain solutions and prices against requirements and criteria that have already been formulated | yes: an answer is an offer; acceptance creates a contract |
| RFQ — request for quotations | obtain a price for a volume that is already clearly defined | an answer is a quotation, not an offer; the contract follows after acceptance |
The US Federal Acquisition Regulation (FAR) states it directly: an RFI is used when there is no intention to award a contract yet, but prices, timelines and market data are needed for planning. There is no prescribed form for an RFI, and answers are not considered offers.
What goes into an RFI
- a description of the task and its context: what the customer wants to achieve and what constraints exist;
- questions about the market: which solutions and technologies exist, how others have applied them, which pitfalls are known;
- what is asked of the respondent: a description of experience, a list of capabilities, sometimes a rough cost estimate;
- the format and deadline for responses and contacts for questions.
Example: a hospital plans to replace its time and attendance system and does not know what to choose — a ready-made cloud service or custom development. Through an RFI it collects a dozen responses from the market in two to three weeks, from which it is clear which products exist at all, how much integration with HR systems costs and which requirements suppliers usually put forward. Only after that are the technical specification and the RFP written.
When an RFI is useful and when it is superfluous
- useful when the task is new and there are no requirements yet: the market will suggest what is possible at all;
- useful before a large procurement: correcting the approach before the RFP is cheaper than after the contract;
- superfluous when the scope is already clear: it is enough to collect quotations straight away through an RFQ;
- superfluous if the market is already studied: answers from the same suppliers as a year ago will add nothing new.
Sources
the term is written from these pages- 48 CFR § 15.201 — Exchange of information with industryacquisition.gov/far/15.201(opens in a new tab)
- 48 CFR § 10.002 — Procedures (market research)acquisition.gov/far/10.002(opens in a new tab)
- CWE-98: Improper Control of Filename for Use in Include Callscwe.mitre.org/data/definitions/98.html(opens in a new tab)
Verified 9 Nov